тАЬAssistance to General Farmers for Sinking Tubewell" was launched by the Dept of Agriculture and Farmer's Welfare, UT of Puducherry. Through this scheme, the farmers from the Gener...
**65% subsidy** towards construction of tubewell/filter point in the Union Territory of Puducherry subject to a maximum of тВ╣1,50,000 per tubewell/filter point per individual.
***The total cost incurred towards the construction of the tubewell shall be taken into account for the calculation of the subsidy.**
The applicant must obtain the necessary permit to sink a new/replacement tubewell/filter point from Pondicherry Ground Water Authority, Puducherry.
The tubewell/Filter point should have been constructed through a departmental power rig/hand bore set or should have been constructed with a No Objection Certificate of the Agriculture Department for engaging private drilling machinery registered with Pondicherry Ground Water Authority under departmental supervision.
The applicant should hold a minimum of 1.5 acres of land under the command area of the tubewell/filter point to be constructed.
The applicant should have ownership of the land for at least 2 years and a clear ownership title deed in his/her name. The eligible land holding of 1.5 acres should be in favour of the applicant farmer, spouse, or a member of the joint/undivided family.
Farmers who have already availed themselves of the subsidy for the same purpose within 5 years are not entitled to any benefit under this scheme.
The casing pipes should have a BIS certificate and should have been purchased from an authorized dealer/ M/s.PASIC Ltd.
The applicant should not convert the lands for a minimum period of 10 years from the date of construction of the tubewell/filter point to any purpose other than agriculture and should execute a bond accordingly.
рдЖрд╡реЗрджрди рдХреИрд╕реЗ рдХрд░реЗрдВ
**Offline**
**Step 1:** The applicant must obtain the mandatory PERMIT for the construction of a new / replacement tubewell from the Pondicherry Ground Water Authority, Puducherry.
**Step 2:** The applicant of the Puducherry region should approach the concerned office towards the construction of the tubewell by deploying departmental machinery.
The applicants who want to construct the tubewell through private machinery should approach the concerned office to get NOC.
**Step 3:** After obtaining NOC, the farmer has to construct a tubewell by deploying private machinery which is registered with Pondicherry Ground Water Authority, Puducherry.
Inspection will be conducted by the Agricultural Officer (Engg.) concerned at the time of the construction of the tubewell to ascertain the details of pipes and other materials used.
**Step 4:** After successful completion of the tubewell/filter point construction work under departmental supervision, the interested applicant should visit (during office hours) the concerned office and request the hard copy of the [prescribed format](https://agri.py.gov.in/sites/default/files/forms/persinwell.pdf) of the application form from the concerned authority:
- **Puducherry:** Office of the HydrogeologistтАРII, State Ground Water Unit & Soil Conservation, Thattanchavady, PuducherryтАР9.- **Karaikal:** Office of the Additional Director of Agriculture, Karaikal.
- The applicant must obtain the necessary permit to sink a new/replacement tubewell/filter point from Pondicherry Ground Water Authority, Puducherry.
- The tubewell/Filter point should have been constructed through a departmental power rig/hand bore set or should have been constructed with...
- **65% subsidy** towards construction of tubewell/filter point in the Union Territory of Puducherry subject to a maximum of тВ╣1,50,000 per tubewell/filter point per individual.
***The total cost incurred towards the construction of the tubewell shall be taken into account for the calculati...
**Offline**
**Step 1:** The applicant must obtain the mandatory PERMIT for the construction of a new / replacement tubewell from the Pondicherry Ground Water Authority, Puducherry.
**Step 2:** The applicant of the Puducherry region should approach the concerned office towards the construct...