1. Simple Explanation

In problems of Time & Work we treat “work” as a quantity that can be added and that can be completed by one or more workers (or machines, people, etc.) at a given rate.

Symbol Meaning Units
(W) Total work (job) units
(R) Rate of a worker (how much work he/she completes per unit time) units/time
(T) Time required time

The basic relationship is

[ \boxed{,W = R \times T,} ]

Thus, if we know any two of (W, R, T) we can find the third. In most test questions the “total work” (W) is not given explicitly; we treat it as 1 job (or use a convenient common multiple).


2. Key Points & Formulas

Situation Formula Explanation
Single worker (T = \dfrac{W}{R}) Time = Job / Rate
Two workers working together (T = \dfrac{W}{R_a + R_b}) Sum of rates
Work done by one worker in given time (W_{a} = R_a \times t)
Work done by one worker in given time, given other worker’s time (R_a = \dfrac{W}{T_a})
Work done in n days by m workers (W = m \times R \times n)
Time when workers work sequentially Add individual times: (T = T_a + T_b + \dots)
When a worker stops before job is finished Subtract his/her contribution: (W_{\text{remaining}} = W - R_a T_a)
Work done by one worker when the other works for a part of the job (R_a = \dfrac{W_{\text{done by a}}}{T_a})
Working with fractions of a job Treat job as 1 unit; fractions are fine: e.g., 2/3 of a job = 0.666…
Rate of one worker in terms of another If (R_a : R_b = p : q), then (R_a = \dfrac{p}{p+q} R_{\text{total}})

Common Tricks

  1. Assume the job is 1 unit – simplifies calculations.
  2. Find common multiples when converting “days” or “hours” to “units per hour” etc.
  3. “Work done by one worker in a given time” is often the easiest starting point.
  4. Check units – keep all rates in same time unit (e.g., per day, per hour).
  5. Use diagrams for sequential work: draw a timeline or a flow chart.

3. Worked Example (Full Solution)

Problem

A can complete a job in 20 days. B can complete the same job in 30 days.
They work together for 4 days, after which A leaves.
B then works alone to finish the job.
Question: How many days will B take to finish the job alone after A leaves?

Step‑by‑Step

  1. Find individual rates

    • Job = 1 unit
    • (R_A = \dfrac{1}{20}) units/day
    • (R_B = \dfrac{1}{30}) units/day
  2. Work done together for 4 days
    [ W_{\text{together}} = (R_A + R_B) \times 4 = \left(\dfrac{1}{20} + \dfrac{1}{30}\right) \times 4 = \left(\dfrac{3+2}{60}\right) \times 4 = \dfrac{5}{60} \times 4 = \dfrac{1}{3}\ \text{unit} ]

  3. Remaining work
    [ W_{\text{remaining}} = 1 - \dfrac{1}{3} = \dfrac{2}{3}\ \text{unit} ]

  4. Time for B alone to finish remaining work
    [ T_B = \dfrac{W_{\text{remaining}}}{R_B} = \dfrac{\dfrac{2}{3}}{\dfrac{1}{30}} = \dfrac{2}{3} \times 30 = 20\ \text{days} ]

  5. Answer – B will need 20 days after A leaves.


4. Quick Revision Summary (Bullet Points)

  • Work = Rate × Time – basic equation.
  • Treat the whole job as 1 unit (unless otherwise specified).
  • Rate of a worker = ( \dfrac{1}{\text{days to finish job}} ).
  • For combined work, add individual rates.
  • For sequential work, add times or subtract contributions.
  • Always keep units consistent (days, hours, etc.).
  • Use common multiples to simplify fractions.
  • Check the answer by plugging back into the basic equation.
  • Practice problems:
    1. Two workers finish a job in 12 days. One of them alone takes 20 days. How long together?
    2. A completes a job in 15 days, B in 25 days. They work together for 5 days, then B leaves. How long does B need to finish the rest?
    3. Three workers

Your note

Page 1

Doubt hai is topic me?

Free AI teacher se poocho — 24/7, step by step.