Time & Work – JEST Quantitative Aptitude Study Notes
(Prepared for JEST – Junior Executive Selection Test)
1. Simple Explanation
In problems of Time & Work we treat “work” as a quantity that can be added and that can be completed by one or more workers (or machines, people, etc.) at a given rate.
| Symbol | Meaning | Units |
|---|---|---|
| (W) | Total work (job) | units |
| (R) | Rate of a worker (how much work he/she completes per unit time) | units/time |
| (T) | Time required | time |
The basic relationship is
[ \boxed{,W = R \times T,} ]
Thus, if we know any two of (W, R, T) we can find the third. In most test questions the “total work” (W) is not given explicitly; we treat it as 1 job (or use a convenient common multiple).
2. Key Points & Formulas
| Situation | Formula | Explanation |
|---|---|---|
| Single worker | (T = \dfrac{W}{R}) | Time = Job / Rate |
| Two workers working together | (T = \dfrac{W}{R_a + R_b}) | Sum of rates |
| Work done by one worker in given time | (W_{a} = R_a \times t) | |
| Work done by one worker in given time, given other worker’s time | (R_a = \dfrac{W}{T_a}) | |
| Work done in n days by m workers | (W = m \times R \times n) | |
| Time when workers work sequentially | Add individual times: (T = T_a + T_b + \dots) | |
| When a worker stops before job is finished | Subtract his/her contribution: (W_{\text{remaining}} = W - R_a T_a) | |
| Work done by one worker when the other works for a part of the job | (R_a = \dfrac{W_{\text{done by a}}}{T_a}) | |
| Working with fractions of a job | Treat job as 1 unit; fractions are fine: e.g., 2/3 of a job = 0.666… | |
| Rate of one worker in terms of another | If (R_a : R_b = p : q), then (R_a = \dfrac{p}{p+q} R_{\text{total}}) |
Common Tricks
- Assume the job is 1 unit – simplifies calculations.
- Find common multiples when converting “days” or “hours” to “units per hour” etc.
- “Work done by one worker in a given time” is often the easiest starting point.
- Check units – keep all rates in same time unit (e.g., per day, per hour).
- Use diagrams for sequential work: draw a timeline or a flow chart.
3. Worked Example (Full Solution)
Problem
A can complete a job in 20 days. B can complete the same job in 30 days.
They work together for 4 days, after which A leaves.
B then works alone to finish the job.
Question: How many days will B take to finish the job alone after A leaves?
Step‑by‑Step
-
Find individual rates
- Job = 1 unit
- (R_A = \dfrac{1}{20}) units/day
- (R_B = \dfrac{1}{30}) units/day
-
Work done together for 4 days
[ W_{\text{together}} = (R_A + R_B) \times 4 = \left(\dfrac{1}{20} + \dfrac{1}{30}\right) \times 4 = \left(\dfrac{3+2}{60}\right) \times 4 = \dfrac{5}{60} \times 4 = \dfrac{1}{3}\ \text{unit} ] -
Remaining work
[ W_{\text{remaining}} = 1 - \dfrac{1}{3} = \dfrac{2}{3}\ \text{unit} ] -
Time for B alone to finish remaining work
[ T_B = \dfrac{W_{\text{remaining}}}{R_B} = \dfrac{\dfrac{2}{3}}{\dfrac{1}{30}} = \dfrac{2}{3} \times 30 = 20\ \text{days} ] -
Answer – B will need 20 days after A leaves.
4. Quick Revision Summary (Bullet Points)
- Work = Rate × Time – basic equation.
- Treat the whole job as 1 unit (unless otherwise specified).
- Rate of a worker = ( \dfrac{1}{\text{days to finish job}} ).
- For combined work, add individual rates.
- For sequential work, add times or subtract contributions.
- Always keep units consistent (days, hours, etc.).
- Use common multiples to simplify fractions.
- Check the answer by plugging back into the basic equation.
- Practice problems:
- Two workers finish a job in 12 days. One of them alone takes 20 days. How long together?
- A completes a job in 15 days, B in 25 days. They work together for 5 days, then B leaves. How long does B need to finish the rest?
- Three workers