PTE /Quantitative Aptitude

Time & work

Commercial Maths · free study notes · Updated

Time & Work – Quantitative Aptitude Notes

(PTE – Test Preparation)


1. Simple Explanation

  • Work – The amount of job that has to be finished.
  • Rate (R) – How much work a person/machine can do per unit time.
  • Time (T) – How long it takes to finish the job.

The basic relationship is

[ \boxed{ \text{Work} ; (W) = \text{Rate} ; (R) \times \text{Time} ; (T) } ]

or, equivalently,

[ \boxed{ R = \frac{W}{T} } \qquad \boxed{ T = \frac{W}{R} } ]

When several workers/machines work together, their rates simply add:

[ R_{\text{total}} = R_1 + R_2 + R_3 + \dots ]


2. Key Points & Tips

Concept What to remember Quick check
Unit consistency Work in units, rate in units/time, time in time. Convert all quantities to the same units.
Work done = Rate × Time Use when you know any two of the three variables. If “time” is in days, “rate” should be “units/day”.
Combined rates Add rates of all workers/machines. Total rate = R1 + R2
Partial work Subtract work done from total to get remaining work. Remaining work = W - (R × T)
Switching workers Split the job into stages, solve each stage separately. Treat each stage as a new “work” problem.
Work per hour/minute Often given as “x parts in 1 hour”. Convert to “part per day” if needed: rate = parts/hour × 24.
Dead time / idle Subtract idle time before calculating rate. Effective time = total time – idle time
All workers start together Use combined rate for the whole period. T = W / (R1 + R2 + …)
All workers finish together Work may be split proportionally to rates. Work_i = (R_i / R_total) × W
Reversed scenario “If X works y days, and Z works the rest” → solve for unknown. Use algebra: T_total = y + (remaining work / R_Z)

3. Worked Example

Problem
Two workers, A and B, can finish a job in 12 days and 8 days respectively.
They work together for 3 days. After that, A leaves and B continues alone.
How many days will B take to finish the remaining work?

Step‑by‑Step

Step What to do Calculation
1. Find individual rates Rate = 1 job / days ( R_A = \frac{1}{12}) job/day, ( R_B = \frac{1}{8}) job/day
2. Find combined rate ( R_{\text{AB}} = R_A + R_B ) ( \frac{1}{12} + \frac{1}{8} = \frac{2}{24} + \frac{3}{24} = \frac{5}{24}) job/day
3. Work done in first 3 days ( W_{\text{first}} = R_{\text{AB}} \times 3 ) ( \frac{5}{24} \times 3 = \frac{15}{24} = \frac{5}{8}) job
4. Remaining work ( W_{\text{remain}} = 1 - W_{\text{first}} ) ( 1 - \frac{5}{8} = \frac{3}{8}) job
5. Time for B alone ( T_B = \frac{W_{\text{remain}}}{R_B} ) ( \frac{3/8}{1/8} = 3) days
6. Total time ( T_{\text{total}} = 3 + 3 = 6) days Answer: B needs 3 more days, total 6 days.

4. Quick Revision Summary

Question type Formula / Idea Example
Single worker ( T = \frac{W}{R} ) One worker takes 20 days → ( R = \frac{1}{20}) job/day
Two workers together ( T = \frac{W}{R_1 + R_2} ) A (12d) + B (8d) → ( T = \frac{1}{5/24} = 4.8) days
Worker leaves mid‑job Split job: compute work in first stage, subtract, solve for remaining