Time & Work – Quantitative Aptitude Notes
(PTE – Test Preparation)
1. Simple Explanation
- Work – The amount of job that has to be finished.
- Rate (R) – How much work a person/machine can do per unit time.
- Time (T) – How long it takes to finish the job.
The basic relationship is
[ \boxed{ \text{Work} ; (W) = \text{Rate} ; (R) \times \text{Time} ; (T) } ]
or, equivalently,
[ \boxed{ R = \frac{W}{T} } \qquad \boxed{ T = \frac{W}{R} } ]
When several workers/machines work together, their rates simply add:
[ R_{\text{total}} = R_1 + R_2 + R_3 + \dots ]
2. Key Points & Tips
| Concept | What to remember | Quick check |
|---|---|---|
| Unit consistency | Work in units, rate in units/time, time in time. | Convert all quantities to the same units. |
| Work done = Rate × Time | Use when you know any two of the three variables. | If “time” is in days, “rate” should be “units/day”. |
| Combined rates | Add rates of all workers/machines. | Total rate = R1 + R2 |
| Partial work | Subtract work done from total to get remaining work. | Remaining work = W - (R × T) |
| Switching workers | Split the job into stages, solve each stage separately. | Treat each stage as a new “work” problem. |
| Work per hour/minute | Often given as “x parts in 1 hour”. | Convert to “part per day” if needed: rate = parts/hour × 24. |
| Dead time / idle | Subtract idle time before calculating rate. | Effective time = total time – idle time |
| All workers start together | Use combined rate for the whole period. | T = W / (R1 + R2 + …) |
| All workers finish together | Work may be split proportionally to rates. | Work_i = (R_i / R_total) × W |
| Reversed scenario | “If X works y days, and Z works the rest” → solve for unknown. | Use algebra: T_total = y + (remaining work / R_Z) |
3. Worked Example
Problem
Two workers, A and B, can finish a job in 12 days and 8 days respectively.
They work together for 3 days. After that, A leaves and B continues alone.
How many days will B take to finish the remaining work?
Step‑by‑Step
| Step | What to do | Calculation |
|---|---|---|
| 1. Find individual rates | Rate = 1 job / days | ( R_A = \frac{1}{12}) job/day, ( R_B = \frac{1}{8}) job/day |
| 2. Find combined rate | ( R_{\text{AB}} = R_A + R_B ) | ( \frac{1}{12} + \frac{1}{8} = \frac{2}{24} + \frac{3}{24} = \frac{5}{24}) job/day |
| 3. Work done in first 3 days | ( W_{\text{first}} = R_{\text{AB}} \times 3 ) | ( \frac{5}{24} \times 3 = \frac{15}{24} = \frac{5}{8}) job |
| 4. Remaining work | ( W_{\text{remain}} = 1 - W_{\text{first}} ) | ( 1 - \frac{5}{8} = \frac{3}{8}) job |
| 5. Time for B alone | ( T_B = \frac{W_{\text{remain}}}{R_B} ) | ( \frac{3/8}{1/8} = 3) days |
| 6. Total time | ( T_{\text{total}} = 3 + 3 = 6) days | Answer: B needs 3 more days, total 6 days. |
4. Quick Revision Summary
| Question type | Formula / Idea | Example |
|---|---|---|
| Single worker | ( T = \frac{W}{R} ) | One worker takes 20 days → ( R = \frac{1}{20}) job/day |
| Two workers together | ( T = \frac{W}{R_1 + R_2} ) | A (12d) + B (8d) → ( T = \frac{1}{5/24} = 4.8) days |
| Worker leaves mid‑job | Split job: compute work in first stage, subtract, solve for remaining |