Bihar Police Sub-Inspector (SI) /Quantitative Aptitude

Time & work

Commercial Maths · free study notes

Time & Work – Bihar Police SI (Quantitative Aptitude)

Why it matters
The Time & Work section tests your ability to model real–world problems with simple algebra.
In the SI exam, problems often involve multiple workers / machines / boats / workers & machines working in tandem or in opposition. A firm grasp of rates, work, and the “work is proportional to rate × time” principle will save you time and prevent common pitfalls.


1. Core Principle

Quantity Symbol Meaning
Work performed (W) Total amount of job (e.g., number of bricks, liters of paint, kilometres).
Rate of a worker/machine (R) Work done per unit time (e.g., bricks per hour).
Time spent (T) Duration of work (usually in hours).
Fundamental Relation (\displaystyle W = R \times T) Work equals rate times time.

Think of rate as “speed” in work‑space.
If two workers are working together, their rates add.
If one is working against another (e.g., two people digging a pit that then refills by rain), you subtract the rates.


2. Key Formulas

Scenario Formula Explanation
Single worker (T = \dfrac{W}{R}) Time = Work ÷ Rate.
Two workers together (T = \dfrac{W}{R_1 + R_2}) Combined rate = sum of individual rates.
Two workers sequentially (T = \dfrac{W}{R_1} + \dfrac{W}{R_2}) Add the times for each worker separately.
Work done by a worker in (t) hours (W_{\text{done}} = R \times t) Simple product.
Work remaining after (t) hours (W_{\text{rem}} = W - R \times t) Subtract what’s done.
One worker’s rate in terms of another If (R_1 : R_2 = a : b) then (R_1 = a \times k, R_2 = b \times k) Introduce a common factor (k).
Work done by machines (W = \frac{T}{\text{cycle time}}) Machines often work in cycles (e.g., a machine fills 10 L in 2 min).
Opposite rates (T = \dfrac{W}{ R_1 - R_2

3. Derivations & Reasoning

3.1 Rate Addition

Let worker A’s rate be (R_A) and worker B’s rate be (R_B).
In 1 hour, A does (R_A) units, B does (R_B) units.
Together, per hour they do (R_A+R_B) units.
Hence, for total work (W),

[ T = \frac{W}{R_A+R_B} ]

3.2 Sequential Work

If A works for (t_A) hours and B for (t_B) hours:

[ \text{Work done} = R_A t_A + R_B t_B = W ]

Solve for unknowns accordingly.

3.3 Opposite Work

Suppose A digs a pit (rate (R_d)) and rain refills it (rate (R_f)).
Net rate = (R_d - R_f) (assuming (R_d > R_f)).
Total time to fill the pit:

[ T = \frac{W}{R_d - R_f} ]


4. Tricky Points & Common Mistakes

Mistake Why it’s wrong Fix
Adding times instead of rates Confusing “together” with “sequentially”. Add rates when workers work simultaneously.
Ignoring units Mixing hours with minutes or litres with kilograms. Convert all times to same unit (usually hours).
Symmetry error Assuming the work done by A in 5 hrs equals B’s work in 10 hrs when rates differ. Use the ratio of rates: (W_A : W_B = R_A : R_B).
Opposite rate mis‑sign Subtracting the wrong rate (e.g., (R_d - R_f) when (R_f > R_d)). Always take absolute value: (
Not checking feasibility Getting a negative time or a rate > 100% of capacity. Verify that all derived values lie in realistic bounds.

5. Worked Example

Problem
Two workers, A and B, can complete a task in 8 hrs and 12 hrs respectively.
They start working together. After 3 hrs, worker B leaves.
How many more hours will A need to finish the task?

Step‑by‑Step

  1. Find rates
    [ R_A = \frac{W}{8}, \qquad R_B = \frac{W}{12} ]

  2. Work done together in 3 hrs
    [ W_{\text{done}} = (R_A + R_B)\times 3 = \left(\frac{W}{8} + \frac{W}{12}\right) \times 3 = \frac{W}{4} ]

  3. Work remaining
    [

Your note

Page 1

Doubt hai is topic me?

Free AI teacher se poocho — 24/7, step by step.