Time & Work – Bihar Police SI (Quantitative Aptitude)
Why it matters
The Time & Work section tests your ability to model real–world problems with simple algebra.
In the SI exam, problems often involve multiple workers / machines / boats / workers & machines working in tandem or in opposition. A firm grasp of rates, work, and the “work is proportional to rate × time” principle will save you time and prevent common pitfalls.
1. Core Principle
| Quantity | Symbol | Meaning |
|---|---|---|
| Work performed | (W) | Total amount of job (e.g., number of bricks, liters of paint, kilometres). |
| Rate of a worker/machine | (R) | Work done per unit time (e.g., bricks per hour). |
| Time spent | (T) | Duration of work (usually in hours). |
| Fundamental Relation | (\displaystyle W = R \times T) | Work equals rate times time. |
Think of rate as “speed” in work‑space.
If two workers are working together, their rates add.
If one is working against another (e.g., two people digging a pit that then refills by rain), you subtract the rates.
2. Key Formulas
| Scenario | Formula | Explanation |
|---|---|---|
| Single worker | (T = \dfrac{W}{R}) | Time = Work ÷ Rate. |
| Two workers together | (T = \dfrac{W}{R_1 + R_2}) | Combined rate = sum of individual rates. |
| Two workers sequentially | (T = \dfrac{W}{R_1} + \dfrac{W}{R_2}) | Add the times for each worker separately. |
| Work done by a worker in (t) hours | (W_{\text{done}} = R \times t) | Simple product. |
| Work remaining after (t) hours | (W_{\text{rem}} = W - R \times t) | Subtract what’s done. |
| One worker’s rate in terms of another | If (R_1 : R_2 = a : b) then (R_1 = a \times k, R_2 = b \times k) | Introduce a common factor (k). |
| Work done by machines | (W = \frac{T}{\text{cycle time}}) | Machines often work in cycles (e.g., a machine fills 10 L in 2 min). |
| Opposite rates | (T = \dfrac{W}{ | R_1 - R_2 |
3. Derivations & Reasoning
3.1 Rate Addition
Let worker A’s rate be (R_A) and worker B’s rate be (R_B).
In 1 hour, A does (R_A) units, B does (R_B) units.
Together, per hour they do (R_A+R_B) units.
Hence, for total work (W),
[ T = \frac{W}{R_A+R_B} ]
3.2 Sequential Work
If A works for (t_A) hours and B for (t_B) hours:
[ \text{Work done} = R_A t_A + R_B t_B = W ]
Solve for unknowns accordingly.
3.3 Opposite Work
Suppose A digs a pit (rate (R_d)) and rain refills it (rate (R_f)).
Net rate = (R_d - R_f) (assuming (R_d > R_f)).
Total time to fill the pit:
[ T = \frac{W}{R_d - R_f} ]
4. Tricky Points & Common Mistakes
| Mistake | Why it’s wrong | Fix |
|---|---|---|
| Adding times instead of rates | Confusing “together” with “sequentially”. | Add rates when workers work simultaneously. |
| Ignoring units | Mixing hours with minutes or litres with kilograms. | Convert all times to same unit (usually hours). |
| Symmetry error | Assuming the work done by A in 5 hrs equals B’s work in 10 hrs when rates differ. | Use the ratio of rates: (W_A : W_B = R_A : R_B). |
| Opposite rate mis‑sign | Subtracting the wrong rate (e.g., (R_d - R_f) when (R_f > R_d)). | Always take absolute value: ( |
| Not checking feasibility | Getting a negative time or a rate > 100% of capacity. | Verify that all derived values lie in realistic bounds. |
5. Worked Example
Problem
Two workers, A and B, can complete a task in 8 hrs and 12 hrs respectively.
They start working together. After 3 hrs, worker B leaves.
How many more hours will A need to finish the task?
Step‑by‑Step
-
Find rates
[ R_A = \frac{W}{8}, \qquad R_B = \frac{W}{12} ] -
Work done together in 3 hrs
[ W_{\text{done}} = (R_A + R_B)\times 3 = \left(\frac{W}{8} + \frac{W}{12}\right) \times 3 = \frac{W}{4} ] -
Work remaining
[