Time & Work – Quantitative Aptitude (Bihar TET)

Goal – Understand the core concepts, solve problems efficiently, and master the most frequently asked question patterns.


1. Simple Explanation

  • Work = The amount of job that can be completed.
  • Rate of work = Work done per unit time (e.g., jobs per hour).
  • Time taken = How long it takes to finish a job at a given rate.

The fundamental relationship:

[ \text{Work} = \text{Rate} \times \text{Time} ]

Key Idea – When you know any two of the three quantities (work, rate, time), you can find the third.


2. Core Concepts & Key Points

Concept Formula How to use
Rate of a single worker (\displaystyle r = \frac{W}{t}) Work (W) divided by time (t) gives the rate.
Combined rate (\displaystyle r_{\text{total}} = r_1 + r_2 + \dots + r_n) Add individual rates to get the joint rate.
Time for group work (\displaystyle t_{\text{total}} = \frac{W}{r_{\text{total}}}) Divide total work by combined rate.
Work done by a worker in a given time (\displaystyle \text{Work}_{\text{done}} = r \times t) Multiply rate by time.
Work done by a worker in a given time when rate changes Compute each segment separately and sum. Example: Worker A does 1/4 of job in 2 hrs, then 1/6 in 3 hrs.
Work left after a period (W_{\text{left}} = W - \text{Work}_{\text{done}}) Subtract completed work from total.
Replacement / Taking over If A does part, then B takes over, compute each part separately. Use addition of work done.
Work with “cannot work alone” Example: A needs B to complete job; treat as a joint rate problem. Set up equation: (r_A + r_B = \frac{W}{T}).

Common Problem Types

  1. Single vs. Multiple Workers – Find time for 1 worker given the time for 2 workers, etc.
  2. Mixed Rates – Two or more workers work for different durations (e.g., Worker A works 2 h, then Worker B works 3 h).
  3. Joint Work with One Worker Inactive – One worker cannot work alone; must pair with another.
  4. Work with Machines/Tools – Machines may have a fixed rate, or their rate may be affected by downtime.
  5. Work and Productivity Ratios – “Worker X does 3/4 of the job in the same time as Y.”
    Convert to rates: (r_X = \frac{3}{4}\frac{W}{T}), (r_Y = \frac{W}{T}).

3. Worked Example

Problem
A and B together can complete a job in 12 days. If B alone can finish the same job in 20 days, how many days will A alone take?

Step-by-Step Solution

  1. Define Variables

    • (W) = total work (let (W = 1) job).
    • (r_A) = rate of A (jobs/day).
    • (r_B) = rate of B.
  2. Write Known Relations

    • (r_B = \frac{1}{20}) (since B takes 20 days for 1 job).
    • (r_A + r_B = \frac{1}{12}) (A & B together finish 1 job in 12 days).
  3. Solve for (r_A)
    [ r_A = \frac{1}{12} - \frac{1}{20} ] Find common denominator 60: [ r_A = \frac{5}{60} - \frac{3}{60} = \frac{2}{60} = \frac{1}{30} ]

  4. Find Time for A Alone
    Since rate (r_A = \frac{1}{30}) job/day, time (t_A = \frac{1}{r_A} = 30) days.

Answer: A alone takes 30 days.


4. Quick Revision Summary

  • Rate = Work ÷ Time.
  • Combined Rate = Sum of individual rates.
  • Time (group) = Total Work ÷ Combined Rate.
  • Work Done = Rate × Time.
  • When One Worker Is Inactive – Treat as a joint rate problem; often requires setting up an equation.
  • Typical Tricks
    • Convert all work to “1 job” for simplicity.
    • Use least common multiples when adding rates.
    • Check units consistently (hrs, days, etc.).
    • Verify by back‑substitution (plug answer back to confirm).
  • Common Pitfalls
    • Mixing units (hours vs days).
    • Forgetting to subtract work already done when calculating remaining time.
    • Treating “can’t work alone” as though the worker can; always account for the joint rate condition.

Quick Practice Question

If 3 workers can finish a job in 15 days, and the same job is finished by 5 workers in 9 days, how many workers are required to finish the job in 6 days?

Answer (fast):
( \text{Rate}{3} = \frac{1}{15}), ( \text{Rate}{5} = \frac{1}{9}).
Let (n) workers finish in 6 days ⇒ ( \frac{n}{6} = \frac{1}{15} \text{?})
Compute combined rate needed: (r_{\text{needed}} = \