Time & Work – Quantitative Aptitude (Bihar TET)
Goal – Understand the core concepts, solve problems efficiently, and master the most frequently asked question patterns.
1. Simple Explanation
- Work = The amount of job that can be completed.
- Rate of work = Work done per unit time (e.g., jobs per hour).
- Time taken = How long it takes to finish a job at a given rate.
The fundamental relationship:
[ \text{Work} = \text{Rate} \times \text{Time} ]
Key Idea – When you know any two of the three quantities (work, rate, time), you can find the third.
2. Core Concepts & Key Points
| Concept | Formula | How to use |
|---|---|---|
| Rate of a single worker | (\displaystyle r = \frac{W}{t}) | Work (W) divided by time (t) gives the rate. |
| Combined rate | (\displaystyle r_{\text{total}} = r_1 + r_2 + \dots + r_n) | Add individual rates to get the joint rate. |
| Time for group work | (\displaystyle t_{\text{total}} = \frac{W}{r_{\text{total}}}) | Divide total work by combined rate. |
| Work done by a worker in a given time | (\displaystyle \text{Work}_{\text{done}} = r \times t) | Multiply rate by time. |
| Work done by a worker in a given time when rate changes | Compute each segment separately and sum. | Example: Worker A does 1/4 of job in 2 hrs, then 1/6 in 3 hrs. |
| Work left after a period | (W_{\text{left}} = W - \text{Work}_{\text{done}}) | Subtract completed work from total. |
| Replacement / Taking over | If A does part, then B takes over, compute each part separately. | Use addition of work done. |
| Work with “cannot work alone” | Example: A needs B to complete job; treat as a joint rate problem. | Set up equation: (r_A + r_B = \frac{W}{T}). |
Common Problem Types
- Single vs. Multiple Workers – Find time for 1 worker given the time for 2 workers, etc.
- Mixed Rates – Two or more workers work for different durations (e.g., Worker A works 2 h, then Worker B works 3 h).
- Joint Work with One Worker Inactive – One worker cannot work alone; must pair with another.
- Work with Machines/Tools – Machines may have a fixed rate, or their rate may be affected by downtime.
- Work and Productivity Ratios – “Worker X does 3/4 of the job in the same time as Y.”
Convert to rates: (r_X = \frac{3}{4}\frac{W}{T}), (r_Y = \frac{W}{T}).
3. Worked Example
Problem
A and B together can complete a job in 12 days. If B alone can finish the same job in 20 days, how many days will A alone take?
Step-by-Step Solution
-
Define Variables
- (W) = total work (let (W = 1) job).
- (r_A) = rate of A (jobs/day).
- (r_B) = rate of B.
-
Write Known Relations
- (r_B = \frac{1}{20}) (since B takes 20 days for 1 job).
- (r_A + r_B = \frac{1}{12}) (A & B together finish 1 job in 12 days).
-
Solve for (r_A)
[ r_A = \frac{1}{12} - \frac{1}{20} ] Find common denominator 60: [ r_A = \frac{5}{60} - \frac{3}{60} = \frac{2}{60} = \frac{1}{30} ] -
Find Time for A Alone
Since rate (r_A = \frac{1}{30}) job/day, time (t_A = \frac{1}{r_A} = 30) days.
Answer: A alone takes 30 days.
4. Quick Revision Summary
- Rate = Work ÷ Time.
- Combined Rate = Sum of individual rates.
- Time (group) = Total Work ÷ Combined Rate.
- Work Done = Rate × Time.
- When One Worker Is Inactive – Treat as a joint rate problem; often requires setting up an equation.
- Typical Tricks
- Convert all work to “1 job” for simplicity.
- Use least common multiples when adding rates.
- Check units consistently (hrs, days, etc.).
- Verify by back‑substitution (plug answer back to confirm).
- Common Pitfalls
- Mixing units (hours vs days).
- Forgetting to subtract work already done when calculating remaining time.
- Treating “can’t work alone” as though the worker can; always account for the joint rate condition.
Quick Practice Question
If 3 workers can finish a job in 15 days, and the same job is finished by 5 workers in 9 days, how many workers are required to finish the job in 6 days?
Answer (fast):
( \text{Rate}{3} = \frac{1}{15}), ( \text{Rate}{5} = \frac{1}{9}).
Let (n) workers finish in 6 days ⇒ ( \frac{n}{6} = \frac{1}{15} \text{?})
Compute combined rate needed: (r_{\text{needed}} = \