Time & Work – Study Notes

(Maharashtra Forest Guard – Quantitative Aptitude)


1. Simple Explanation

  • Time & Work problems ask you to find how long it takes to finish a job or how many workers are needed, given the rates at which they work.
  • Rate of work is the amount of work done in a unit time (e.g., units per hour).
  • Work is a quantity that can be measured in units (e.g., acres of forest, pages of a report).

2. Key Points & Formulas

Symbol Meaning Formula
(R) Rate of work of a person/teams (R = \dfrac{\text{Work}}{\text{Time}})
(T) Time taken to finish a job (T = \dfrac{\text{Work}}{R})
(W) Total work (units) –
(n) Number of workers –
For two workers A & B working together: (R_{\text{total}} = R_A + R_B)
For (n) workers of same rate (R): (R_{\text{total}} = nR)
Work done in time (t): (W_{\text{done}} = R \times t)
Time saved/lost when workers join/leave: Use difference in rates

Important Rules

  1. Inverse Relationship

    • If rate doubles, time halves.
    • If rate is halved, time doubles.
  2. Fraction of Work

    • A worker can complete (\dfrac{1}{R}) of the job in one time unit.
    • If a worker works for (t) units, he completes (\dfrac{t}{R}) of the job.
  3. Combining Workers

    • Sum of individual rates gives the combined rate.
    • Example: A (3/8 job/hr) + B (5/8 job/hr) → Total rate = 1 job/hr → 1 hour to finish.
  4. Partial Work

    • If someone starts and stops, calculate the work done before stopping:
      (\text{Work done} = R \times \text{time}).
    • Subtract from total to find remaining work.
  5. Work & Time Not Independent

    • Work can be any constant (e.g., 1 whole job).
    • Changing the number of workers changes the rate, not the work.

3. Worked Example

Problem (Typical Forest Guard Question)

A forest guard A can clear 120 acres of forest in 8 days. Another guard B can clear the same area in 12 days. How many days will it take for A and B working together to clear the area? Also, if B joins A after 3 days, how many days will they finish together?

Step‑by‑Step Solution

  1. Find individual rates
Guard Work Time (days) Rate (acres/day)
A 120 acres 8 (R_A = \dfrac{120}{8} = 15)
B 120 acres 12 (R_B = \dfrac{120}{12} = 10)
  1. Combined rate when both work together

[ R_{\text{total}} = R_A + R_B = 15 + 10 = 25 \text{ acres/day} ]

  1. Time to finish together (from start)

[ T_{\text{together}} = \frac{\text{Work}}{R_{\text{total}}} = \frac{120}{25} = 4.8 \text{ days} ]

(So they would finish in 4 days 19 h 12 min.)

  1. Scenario: B joins after 3 days

    • Work done by A alone in 3 days

      [ W_{\text{A,3d}} = R_A \times 3 = 15 \times 3 = 45 \text{ acres} ]

    • Remaining work

      [ W_{\text{rem}} = 120 - 45 = 75 \text{ acres} ]

    • Combined rate (A+B) remains 25 acres/day.

    • Time needed after B joins

      [ T_{\text{after3d}} = \frac{W_{\text{rem}}}{R_{\text{total}}} = \frac{75}{25} = 3 \text{ days} ]

  2. Total time from start

[ T_{\text{total}} = 3 \text{ days (A alone)} + 3 \text{ days (A+B)} = 6 \text{ days} ]

Answer:

  • Together from the start: 4.8 days.
  • If B joins after 3 days: 6 days total.

4. Quick Revision Summary

Concept Formula Quick Tip
Work = Rate × Time (W = R \times T) Think of “Rate” as “how many units per day”.
Time = Work / Rate (T = \frac{W}{R}) If you know how fast and how much, you get time.
Combined Rate (R_{\text{total}} = R_1 + R_2 + \dots + R_n) Add the rates of all workers.
Inverse Relationship Double rate → halve time Great for quick mental checks.
Partial Work (W_{\text{done}} = R \times t) Use when someone works for only part of the job.
Work Left (W_{\text{left}} = W_{\text{total}} - W_{\text{done}}) Simple subtraction.

Practice Strategy

  1. Read carefully – identify who works, for how long, and what they are asked to find.
  2. Write down:
    • Total work (often 1 job or a given area).
    • Individual rates (using given times).
  3. Combine rates if needed.
  4. Compute time with the formula (T =