Time & Work – Study Notes
(For West Bengal Police Constable – Quantitative Aptitude)
1. Simple Explanation
Time & Work deals with the relationship between the amount of work done, the number of workers, and the time taken.
- Work rate of a worker = units of work per unit time.
- If a worker A can finish a job in x days, his rate = ( \frac{1}{x} ) job/day.
- For n workers working together, total rate = sum of individual rates.
The basic formula:
[
\text{Work} = \text{Rate} \times \text{Time}
]
or, when using days and workers:
[
\text{Days} = \frac{\text{Total Work (in job units)}}{\text{Total Rate (job/day)}}
]
2. Key Points
| Concept | Symbol | Typical Formula | Common Pitfalls |
|---|---|---|---|
| Rate of one worker | ( R_A ) | ( R_A = \frac{1}{T_A} ) where (T_A) = days taken by A | Forget to convert to per day |
| Combined rate | ( R_{\text{total}} ) | ( R_{\text{total}} = R_A + R_B + \dots ) | Adding rates, not times |
| Work done by a worker in t days | ( W_A ) | ( W_A = R_A \times t ) | Mixing up units |
| Time for n workers | ( T ) | ( T = \frac{1}{R_{\text{total}}} ) or ( T = \frac{Work}{R_{\text{total}}} ) | Assuming equal work distribution without accounting for rates |
| Work left after some workers leave | ( W_{\text{left}} ) | ( W_{\text{left}} = \text{Total Work} - \text{Work done} ) | Forgetting that work done depends on time & rate |
| Relative work | ( R_{\text{diff}} ) | ( R_{\text{diff}} = R_A - R_B ) | Confusing with total rate |
| Partial work | ( W_{\text{partial}} ) | ( W_{\text{partial}} = R_{\text{total}} \times t_{\text{partial}} ) | Units mismatch |
3. Worked Example
Problem
A can finish a job in 20 days, B in 30 days. They work together for 8 days. Then B leaves, and A continues alone. If the job is completed after 12 days of A’s solo work, how many days will it take for B alone to finish the job?
Solution
-
Rates
- ( R_A = \frac{1}{20} ) job/day
- ( R_B = \frac{1}{30} ) job/day
-
Combined rate
[ R_{\text{total}} = \frac{1}{20} + \frac{1}{30} = \frac{3+2}{60} = \frac{5}{60} = \frac{1}{12}\ \text{job/day} ] -
Work done together in 8 days
[ W_{\text{together}} = R_{\text{total}} \times 8 = \frac{1}{12} \times 8 = \frac{8}{12} = \frac{2}{3}\ \text{job} ] -
Work left after 8 days
[ W_{\text{left}} = 1 - \frac{2}{3} = \frac{1}{3}\ \text{job} ] -
A works alone for 12 days
Work done by A alone:
[ W_A = R_A \times 12 = \frac{1}{20} \times 12 = \frac{12}{20} = \frac{3}{5} ]But we know the remaining work after B leaves is (\frac{1}{3}).
Check consistency:
[ \frac{3}{5} \neq \frac{1}{3} ] So the problem statement must mean that after B leaves, A continues for an additional 12 days and the job is finished at that point. Hence the total work after 8 days + 12 days of A =
[ W_{\text{together}} + W_A = \frac{2}{3} + \frac{3}{5} = \frac{10}{15} + \frac{9}{15} = \frac{19}{15} ] This exceeds 1, so the given data are inconsistent.
(In exam settings, double‑check the numbers; if the data are consistent, use the method above.)
Take‑away – Always compute rates first, then work done, then remaining work. Keep track of units.
4. Quick Revision Summary
| Step | What to Do | Formula |
|---|---|---|
| 1. Convert days to rates | ( R = 1/\text{days} ) | |
| 2. Sum rates for all workers | ( R_{\text{total}} = \sum R_i ) | |
| 3. Compute work done in given time | ( W = R_{\text{total}} \times t ) | |
| 4. Find remaining work | ( W_{\text{left}} = 1 - W ) | |
| 5. Compute time for remaining work (if one worker continues) | ( t_{\text{remaining}} = \frac{W_{\text{left}}}{R_{\text{single}}} ) | |
| 6. For ‘work left after some leave’ | Use remaining work formula |
Tips for the exam
- Read each sentence carefully – “after X days” vs. “during X days”.
- Write down the rates before plugging into formulas.
- Check units – days, job/day, job.
- Use common fractions to avoid decimal errors.
- Practice with mixed problems (workers join/leave, part‑time, different efficiencies).
End of Notes