Time & Work – Study Notes
(For Tamil Nadu Police Constable Examination – Quantitative Aptitude)
1. Simple Explanation
The Time & Work topic deals with how long it takes people (or machines, teams, etc.) to finish a job when they work together or separately.
- Work (W): Total amount of job to be done.
- Rate of Work (R): How much of the job one person can finish in one unit of time (e.g., per hour).
- Time (T): How long it takes to finish the job.
The fundamental relation is
[ \text{Rate} \times \text{Time} = \text{Work} \quad\Longrightarrow\quad R \times T = W ]
When several people work together, their rates add up.
2. Key Points
| Concept | Formula | Quick Check |
|---|---|---|
| Single person rate | (R = \frac{1}{T}) (if (W = 1) unit) | If a person finishes a job in 4 hrs → (R = \frac{1}{4}) job/hr |
| Combined rate | (R_{\text{total}} = R_1 + R_2 + \dots + R_n) | Add reciprocals of times |
| Time for combined work | (T_{\text{total}} = \frac{1}{R_{\text{total}}}) | If (R_{\text{total}} = \frac{1}{2}) job/hr → 2 hrs |
| Work done by one person in given time | (W = R \times t) | Use (R = \frac{1}{T_{\text{single}}}) |
| Work left after a period | (W_{\text{left}} = W_{\text{total}} - W_{\text{done}}) | Subtract from 1 if whole job = 1 unit |
| Work in terms of ‘days’ or ‘hours’ | Keep same units throughout | Convert when necessary (e.g., 1 day = 8 hrs) |
| Identical work | If two persons have the same rate, work done = 2 × their individual work | Useful for quick estimates |
| Rest or idle time | Subtract from working hours | If a worker works 6 hrs/day but rests 1 hr → effective 5 hrs |
3. Worked Example
Problem
A and B can complete a task in 12 days and 15 days respectively.
They work together for 5 days, then A leaves.
B continues alone.
How many more days will B need to finish the job?
Step‑by‑step Solution
| Step | Calculation | Result |
|---|---|---|
| 1. Convert to rates (jobs per day) | (R_A = \frac{1}{12}), (R_B = \frac{1}{15}) | (R_A = 0.0833), (R_B = 0.0667) |
| 2. Combined rate | (R_{AB} = R_A + R_B = \frac{1}{12} + \frac{1}{15}) | (R_{AB} = \frac{5}{60} + \frac{4}{60} = \frac{9}{60} = \frac{3}{20}) |
| 3. Work done together in 5 days | (W_{\text{done}} = R_{AB} \times 5 = \frac{3}{20} \times 5 = \frac{15}{20} = \frac{3}{4}) | 75 % of job |
| 4. Work remaining | (W_{\text{left}} = 1 - \frac{3}{4} = \frac{1}{4}) | 25 % of job |
| 5. Time B needs alone | (T_B = \frac{W_{\text{left}}}{R_B} = \frac{1/4}{1/15} = \frac{1}{4} \times 15 = 3.75) days | 3 days 18 hrs |
Answer: B will need 3 days 18 hrs more to finish the task.
4. Quick Revision Summary
| Question | What to do? |
|---|---|
| “Who finishes a job faster?” | Compare rates ((1/T)). Faster person has larger rate. |
| “How long will two people take together?” | Add their rates → find combined rate → take reciprocal. |
| “Work done in a given time?” | Multiply that person’s rate by the time. |
| “Work left after some days?” | Subtract work done from total (1 unit). |
| “Time to finish remaining work?” | Divide remaining work by rate of remaining worker(s). |
| “Convert between days and hours?” | Use conversion factor (1 day = 8 hrs for work‑day, 24 hrs for real day). |
| “Rest or breaks?” | Subtract idle time from actual working time. |
Tips for the Exam
- Always use the same unit (days or hours) for all people involved.
- Write rate as (1/\text{time}) for simplicity.
- Check for “work left” when a worker leaves or joins.
- Round only at the end; keep fractions during calculations.
- Practice with mixed‑unit problems (e.g., one person works 6 hrs/day, another 8 hrs/day).
Good luck with your preparation!