Time & Work – Study Notes

(Punjab TET – Quantitative Aptitude)

Objective – Solve problems where time, work, and rate of work of people/ machines are related.


1. Simple Explanation

Concept Definition Symbol
Work Total amount of job to be done. W
Rate of Work Amount of work done in one unit of time. r or R
Time Duration taken to complete a job. t
Relationship Work = Rate × Time → W = r × t
Unit Work A job that can be completed in 1 unit of time by a worker at rate 1.

Key Idea – Work is a scalar quantity; it can be divided, combined, or distributed among workers/machines.

Example: If a worker can finish a job in 10 days, his rate = 1/10 job per day.


2. Key Points & Formulas

Situation Formula Notes
One worker alone t = W / r If W=1 (unit work) → t = 1/r
Multiple workers together rate_total = Σ rᵢ
t = W / rate_total
Add individual rates.
Workers working in alternating days Compute work done per cycle. Cycle may consist of 1 day by A, 1 day by B, etc.
Work done by one worker in time of another W_A = r_A × t_A Usually W_A + W_B = 1.
Time taken if one worker replaces another t_new = r_original / r_new × t_original Use inverse of rate.
Half‑work, remaining work Find time for first part, then remaining time. Helpful for “first half done by X, remaining by Y” problems.
Partial work by a worker t = (part_of_work) / r Part may be ½, ¼ etc.
Machines & people Treat machine’s rate like a person’s. e.g., “Machine A works 3× faster than worker B”.

Quick Formula Sheet

Symbol Meaning Formula
r₁, r₂, … Individual rates rᵢ = 1 / tᵢ (if W=1)
R Combined rate R = Σ rᵢ
t Time to finish job t = 1 / R (for unit work)
W₁, W₂ Work done by each Wᵢ = rᵢ × tᵢ
k Work fraction k = W₁ / W (e.g., ½, ¼)

3. Worked Example

Problem

A can complete a job in 12 days, B in 18 days. First, A works alone for 3 days, then B works alone for 5 days. How many days will C, who can finish the job in 8 days, need to finish the remaining work?

Step‑by‑Step

  1. Convert to unit work
    Let total work W = 1 (unit job).

    • Rate of A: r_A = 1/12 job/day
    • Rate of B: r_B = 1/18 job/day
    • Rate of C: r_C = 1/8 job/day
  2. Work done by A in 3 days
    W_A = r_A × 3 = (1/12) × 3 = 3/12 = 1/4

  3. Work done by B in 5 days
    W_B = r_B × 5 = (1/18) × 5 = 5/18

  4. Total work done by A + B
    W_AB = 1/4 + 5/18 = (9/36 + 10/36) = 19/36

  5. Remaining work
    W_rem = 1 – W_AB = 1 – 19/36 = 17/36

  6. Time for C to finish remaining work
    t_C = W_rem / r_C = (17/36) ÷ (1/8) = (17/36) × 8 = 136/36 = 3.777… ≈ 3.78 days

    So C needs about 3.78 days (≈ 3 days 19 hours).

Quick Check

  • Total time so far: 3 + 5 = 8 days.
  • Expected total time ≈ 8 + 3.78 = 11.78 days.
  • Compare with A alone: 12 days – close, as C is faster than A.

4. Quick Revision Summary

  • Work = Rate × Time – always start from this relation.
  • Rate of a worker = 1 / (days to finish job) (for unit work).
  • Combined rate = sum of individual rates.
  • Time to finish job = 1 / (combined rate) (for unit work).
  • Work done in a period = rate × time.