Time & Work – Study Notes

For the Punjab Forest Guard – Quantitative Aptitude


1. Simple Explanation

  • Work: Any job that can be measured (e.g., building a wall, filling a tank).
  • Rate of Work: How much work a person/vehicle/etc. can complete per unit time.
    • If a worker completes a whole job in T days, his rate = 1/T jobs/day.
  • Work Done: Amount of work actually completed (often expressed as a fraction of the whole job).
  • Time: Duration taken to finish a job.

Core Relationship

[ \text{Rate} \times \text{Time} = \text{Work} ]

When multiple workers/units work together, their rates add up.


2. Key Points & Formulas

Concept Symbol Formula Example
Work (W) (W = \text{Rate} \times \text{Time}) 1 whole job
Rate of One Person (R_i) (R_i = \frac{1}{T_i}) A finishes in 10 days → (R=1/10)
Combined Rate (R_{\text{tot}}) (R_{\text{tot}} = R_1 + R_2 + \dots + R_n) A(1/10)+B(1/15)
Time for Combined Work (T) (T = \frac{1}{R_{\text{tot}}}) (T = 1/(1/10+1/15)=30/7) days
Work Done by a Person in Time (t) (W_i) (W_i = R_i \times t) 5 days × (1/10) = 1/2 job
Wages/Pay (P) (P = \text{Rate of Work} \times \text{Pay per unit work}) If ₹10 per job, A earns (10 \times 1/10 = ₹1) per day
Efficiency (E_i) (E_i = \frac{W}{T}) If 10 workers finish in 5 days, each worker’s efficiency = 1/5 job/day
Work with Leaving/Joining – Adjust rates or time accordingly If one worker leaves after 2 days, subtract his 2‑day contribution from total work
Complementary Work – Use ( \frac{1}{\text{Time}} ) for combined work A(1/8)+B(1/12)+C(1/20)
Work & Money (Wage Problems) – ( \frac{W_1}{W_2} = \frac{P_1}{P_2} ) Pay proportional to amount of work

3. Worked Example

Problem

A and B can complete a piece of work in 20 days and 30 days respectively.
They start together. After 5 days, C joins, who can finish the same work in 12 days.
Question: How many more days will be required to finish the work after C joins?

Step 1: Find Individual Rates

  • Rate of A: (R_A = 1/20) job/day
  • Rate of B: (R_B = 1/30) job/day
  • Rate of C: (R_C = 1/12) job/day

Step 2: Work Done by A & B in First 5 Days

  • Combined rate of A & B: (R_{AB} = R_A + R_B = \frac{1}{20} + \frac{1}{30} = \frac{3+2}{60} = \frac{5}{60} = \frac{1}{12})
  • Work done in 5 days: (W_{AB} = R_{AB} \times 5 = \frac{1}{12} \times 5 = \frac{5}{12})

So, (\frac{5}{12}) of the job is already finished.

Step 3: Remaining Work

Remaining work (= 1 - \frac{5}{12} = \frac{7}{12})

Step 4: New Combined Rate After C Joins

(R_{\text{total}} = R_A + R_B + R_C = \frac{1}{20} + \frac{1}{30} + \frac{1}{12})

Find common denominator 60:
[ R_{\text{total}} = \frac{3}{60} + \frac{2}{60} + \frac{5}{60} = \frac{10}{60} = \frac{1}{6} ]

So all three together can finish the job in 6 days.

Step 5: Time to Finish Remaining Work

Remaining work = (\frac{7}{12})
Time (t = \frac{\text{Remaining Work}}{R_{\