Haryana Police Constable /Quantitative Aptitude

Time & work

Commercial Maths · free study notes · Updated

Time & Work – Study Notes

For Haryana Police Constable Examination – Quantitative Aptitude


1. Simple Explanation

Time & Work problems involve two or more persons (or machines, etc.) performing a task.

  • Work is the total job that has to be finished.
  • Rate is how fast a person can finish the work (units of work per unit time).
  • Time is how long it takes to finish the work.

The basic relationship is

[ \text{Work} = \text{Rate} \times \text{Time} ]

or, in terms of only two variables when the third is known,

[ \text{Rate} = \frac{\text{Work}}{\text{Time}},\qquad \text{Time} = \frac{\text{Work}}{\text{Rate}} ]

When several people work together, their rates add up:

[ \text{Combined Rate} = R_1 + R_2 + R_3 + \dots ]


2. Key Points & Formulas

Concept Symbol Formula Notes
Rate (R) (R = \dfrac{W}{T}) Units: work per day, per hour, etc.
Time (T) (T = \dfrac{W}{R})
Work (W) (W = R \times T)
Combined rate – (R_{\text{combined}} = R_A + R_B + R_C + \dots) Add rates of all workers
Work done by part of time – (W_{\text{done}} = R \times T_{\text{part}})
Work remaining – (W_{\text{remaining}} = W_{\text{total}} - W_{\text{done}})
If a worker works for a part of the job – (R_{\text{part}} = \dfrac{W_{\text{part}}}{T_{\text{part}}})
Work rate of a person who works x days after another – Use combined rate for first x days, then subtract that portion
Work done when one person stops – Subtract his/her contribution from the combined rate

Common Assumptions

  1. Rates are constant over the period considered.
  2. Work is additive – if one person does 2/5 of the job, another does the rest.
  3. No idle time unless explicitly mentioned.
  4. Units must be consistent (days, hours, etc.).

3. Worked Example

Problem

A can complete a piece of work in 12 days. B can finish the same work in 18 days.
They start together, but after 4 days B leaves. A then works alone for 2 more days.
How many days will it take A and B together to finish the work if B had continued?

Step‑by‑Step

Step Calculation Explanation
1. Find individual rates (R_A = \frac{1}{12}) work/day, (R_B = \frac{1}{18}) work/day Rate = 1 job / days to finish
2. Combined rate (R_{\text{AB}} = R_A + R_B = \frac{1}{12} + \frac{1}{18} = \frac{5}{36}) work/day
3. Work done in first 4 days (both) (W_{\text{first4}} = R_{\text{AB}} \times 4 = \frac{5}{36} \times 4 = \frac{5}{9})
4. Remaining work (W_{\text{rem}} = 1 - \frac{5}{9} = \frac{4}{9})
5. Work done by A in next 2 days (W_{A,2} = R_A \times 2 = \frac{1}{12} \times 2 = \frac{1}{6})
6. Work left after A’s extra 2 days (W_{\text{left}} = \frac{4}{9} - \frac{1}{6} = \frac{8}{18} - \frac{3}{18} = \frac{5}{18})
7. Time needed for A + B to finish remaining work (T_{\text{remaining}} = \frac{W_{\text{left}}}{R_{\text{AB}}} = \frac{5/18}{5/36} = \frac{5}{18} \times \frac{36}{5} = 2) days
8. Total days if B had not left (T_{\text{total}} = 4\text{ days (initial)} + 2\text{ days (extra)} + 2\text{ days (remaining)} = 8) days

Answer: A and B together would finish the work in 8 days if B had not left.


4. Quick Revision Summary

  • Work = Rate × Time – fundamental equation.
  • Find individual rates: (R = \frac{1}{\text{days to finish}}).
  • Add rates for teamwork.
  • Multiply rate by time to get work done.
  • Subtract completed work from total to get remaining work.
  • Always keep units consistent (days, hours).
  • Remember:
    • If someone works for part of