Time & Work – Study Notes
For Haryana Police Constable Examination – Quantitative Aptitude
1. Simple Explanation
Time & Work problems involve two or more persons (or machines, etc.) performing a task.
- Work is the total job that has to be finished.
- Rate is how fast a person can finish the work (units of work per unit time).
- Time is how long it takes to finish the work.
The basic relationship is
[ \text{Work} = \text{Rate} \times \text{Time} ]
or, in terms of only two variables when the third is known,
[ \text{Rate} = \frac{\text{Work}}{\text{Time}},\qquad \text{Time} = \frac{\text{Work}}{\text{Rate}} ]
When several people work together, their rates add up:
[ \text{Combined Rate} = R_1 + R_2 + R_3 + \dots ]
2. Key Points & Formulas
| Concept | Symbol | Formula | Notes |
|---|---|---|---|
| Rate | (R) | (R = \dfrac{W}{T}) | Units: work per day, per hour, etc. |
| Time | (T) | (T = \dfrac{W}{R}) | |
| Work | (W) | (W = R \times T) | |
| Combined rate | – | (R_{\text{combined}} = R_A + R_B + R_C + \dots) | Add rates of all workers |
| Work done by part of time | – | (W_{\text{done}} = R \times T_{\text{part}}) | |
| Work remaining | – | (W_{\text{remaining}} = W_{\text{total}} - W_{\text{done}}) | |
| If a worker works for a part of the job | – | (R_{\text{part}} = \dfrac{W_{\text{part}}}{T_{\text{part}}}) | |
| Work rate of a person who works x days after another | – | Use combined rate for first x days, then subtract that portion | |
| Work done when one person stops | – | Subtract his/her contribution from the combined rate |
Common Assumptions
- Rates are constant over the period considered.
- Work is additive – if one person does 2/5 of the job, another does the rest.
- No idle time unless explicitly mentioned.
- Units must be consistent (days, hours, etc.).
3. Worked Example
Problem
A can complete a piece of work in 12 days. B can finish the same work in 18 days.
They start together, but after 4 days B leaves. A then works alone for 2 more days.
How many days will it take A and B together to finish the work if B had continued?
Step‑by‑Step
| Step | Calculation | Explanation |
|---|---|---|
| 1. Find individual rates | (R_A = \frac{1}{12}) work/day, (R_B = \frac{1}{18}) work/day | Rate = 1 job / days to finish |
| 2. Combined rate | (R_{\text{AB}} = R_A + R_B = \frac{1}{12} + \frac{1}{18} = \frac{5}{36}) work/day | |
| 3. Work done in first 4 days (both) | (W_{\text{first4}} = R_{\text{AB}} \times 4 = \frac{5}{36} \times 4 = \frac{5}{9}) | |
| 4. Remaining work | (W_{\text{rem}} = 1 - \frac{5}{9} = \frac{4}{9}) | |
| 5. Work done by A in next 2 days | (W_{A,2} = R_A \times 2 = \frac{1}{12} \times 2 = \frac{1}{6}) | |
| 6. Work left after A’s extra 2 days | (W_{\text{left}} = \frac{4}{9} - \frac{1}{6} = \frac{8}{18} - \frac{3}{18} = \frac{5}{18}) | |
| 7. Time needed for A + B to finish remaining work | (T_{\text{remaining}} = \frac{W_{\text{left}}}{R_{\text{AB}}} = \frac{5/18}{5/36} = \frac{5}{18} \times \frac{36}{5} = 2) days | |
| 8. Total days if B had not left | (T_{\text{total}} = 4\text{ days (initial)} + 2\text{ days (extra)} + 2\text{ days (remaining)} = 8) days |
Answer: A and B together would finish the work in 8 days if B had not left.
4. Quick Revision Summary
- Work = Rate × Time – fundamental equation.
- Find individual rates: (R = \frac{1}{\text{days to finish}}).
- Add rates for teamwork.
- Multiply rate by time to get work done.
- Subtract completed work from total to get remaining work.
- Always keep units consistent (days, hours).
- Remember:
- If someone works for part of