Time & Work – Quantitative Aptitude
(For Jharkhand TET – Teacher Eligibility Test)
Time & Work deals with the relationship between the amount of work, the rate of work done by one or more workers, and the time taken.
The basic idea: Work = Rate × Time.
1. Simple Explanation
| Concept | Symbol | Formula | Example (one worker) |
|---|---|---|---|
| Work | (W) | (W = r \times t) | A worker finishes a job in 5 hrs → (W = 1) (whole job). |
| Rate | (r) | (r = \dfrac{W}{t}) | (r = \dfrac{1}{5} = 0.2) jobs/hr. |
| Time | (t) | (t = \dfrac{W}{r}) | (t = \dfrac{1}{0.2} = 5) hrs. |
When several workers work together:
(r_{\text{total}} = r_1 + r_2 + \dots + r_n).
Time taken together (t = \dfrac{W}{r_{\text{total}}}).
2. Key Points
| # | Topic | What to remember |
|---|---|---|
| 1 | Work is additive | If A does 1/3 of a job in 9 hrs, B does 1/6 of same job in 12 hrs, together they do 1/3 + 1/6 = 1/2 of job. |
| 2 | Work done in a day | For part‑day work, use fractions: 3 hrs out of 8‑hr day → ( \frac{3}{8}) of daily work. |
| 3 | Inverse relationship | If rate doubles, time halves (assuming work constant). |
| 4 | Work vs Time | Work ∝ 1/Time when rate is constant. |
| 5 | Combined work | (t_{\text{both}} = \frac{1}{\frac{1}{t_A} + \frac{1}{t_B}}) when each alone finishes the job in (t_A, t_B) hrs. |
| 6 | Serial vs Parallel | Serial: one after the other → add times. Parallel: together → use combined rate. |
| 7 | Units | Always keep units consistent (hrs, days, etc.). |
3. Worked Example
Problem
Worker A can complete a job in 12 hrs. Worker B can complete the same job in 18 hrs. They start together. How long will it take them to finish the job?
Step‑by‑Step
-
Compute individual rates
- (r_A = \frac{1 \text{ job}}{12 \text{ hrs}} = \frac{1}{12}) jobs/hr
- (r_B = \frac{1}{18}) jobs/hr
-
Find combined rate
[ r_{\text{total}} = r_A + r_B = \frac{1}{12} + \frac{1}{18} ] Find common denominator (36):
[ r_{\text{total}} = \frac{3}{36} + \frac{2}{36} = \frac{5}{36}\text{ jobs/hr} ] -
Compute time to finish 1 job
[ t = \frac{W}{r_{\text{total}}} = \frac{1}{\frac{5}{36}} = \frac{36}{5} = 7.2 \text{ hrs} ] So they finish the job in 7 hrs 12 min.
Quick check:
In 7.2 hrs, A does (7.2 \times \frac{1}{12}=0.6) job, B does (7.2 \times \frac{1}{18}=0.4) job → total (1.0) job.
4. Quick Revision Summary
| Formula | What it gives | Example usage |
|---|---|---|
| (W = r \times t) | Work done | Find work done by a worker in given time |
| (r = \dfrac{W}{t}) | Rate of work | Convert time to rate |
| (t = \dfrac{W}{r}) | Time required | Find time for given work & rate |
| (r_{\text{total}} = r_1 + r_2 + \dots) | Combined rate | Workers working together |
| (t_{\text{both}} = \dfrac{1}{\frac{1}{t_A} + \frac{1}{t_B}}) | Time for two workers | If each can finish job alone in known times |
| (t_{\text{serial}} = t_A + t_B) | Time when working one after another | Serial tasks |
| (\text{Work done in fraction of day} = \frac{\text{hours worked}}{\text{total working hours}}) | Partial‑day work | 3 hrs of 8‑hr day → (3/8) job |
Quick Tips
- Always convert to the same unit (hrs or days) before adding or dividing.
- Check for “part of the job” vs “whole job” confusion.
Use “(1)” to represent the whole job. - Use fractions early to avoid rounding errors.
- Remember the inverse relationship: doubling rate halves time.
- Serial work → add times; Parallel work → add rates.
Practice Question
*Mr. X can paint