Time & Work – Advanced Study Notes
(Prepared for MIT‑level Quantitative Aptitude, Chhattisgarh PSC)
These notes assume a basic familiarity with algebra and fractions. They aim to build a rigorous, first‑principles understanding of the “time & work” problem, explore deeper theory, discuss edge cases, and present a challenging problem to test mastery.
1. Foundations – Work as a Quantitative Quantity
| Symbol | Meaning | Units (SI) |
|---|---|---|
| (W) | Total work to be done | units of work (e.g., “man‑hours”) |
| (R) | Rate of work of a worker | units of work per unit time |
| (T) | Time taken | time (e.g., hours, days) |
| (n) | Number of workers | dimensionless |
Work–time relation
[
W = R \times T \quad\Longleftrightarrow\quad R = \frac{W}{T}
]
The equation states that work is the product of rate and time, a direct consequence of the definition of “rate” as quantity per unit time.
2. From First Principles – Deriving the Core Formulae
2.1 Single Worker
Let a worker take (T) units of time to finish a job of size (W).
By definition of rate,
[
R = \frac{W}{T} \quad\Rightarrow\quad T = \frac{W}{R}
]
This is the basic time–work formula.
2.2 Multiple Workers Working Simultaneously
Assume (n) workers work together, each with a constant individual rate (R_i).
The joint rate (R_{\text{joint}}) is the sum of individual rates:
[
R_{\text{joint}} = \sum_{i=1}^{n} R_i
]
Hence total time:
[
T = \frac{W}{\displaystyle\sum_{i=1}^{n} R_i}
]
Key Insight: Work rates add linearly because each worker contributes an amount of work per unit time; the total contribution per unit time is the sum.
2.3 Work Done in Parts of the Job
If a job is split into portions (W_1, W_2, \dots, W_k) (not necessarily equal), each portion may be undertaken by different workers or groups.
Let worker (i) work on portion (W_i) for time (T_i). Then:
[
W_i = R_i T_i \quad\text{for each } i
]
And the total job is simply
[
W = \sum_{i=1}^{k} W_i
]
This decomposition is useful for problems where workers start or finish at different times.
2.4 Changing Rates – Productivity Factors
Sometimes a worker’s rate changes (e.g., due to fatigue or efficiency improvement).
Let (R(t)) be the instantaneous rate at time (t).
The total work is the integral
[
W = \int_{0}^{T} R(t), dt
]
In discrete problems, piecewise constant rates are used, leading to sums of the form:
[
W = \sum_{j=1}^{m} R_j \Delta t_j
]
where (R_j) is the rate during interval (\Delta t_j).
3. Deeper Theory – Rate Algebra and Harmonic Means
3.1 Work Rates as Inverse Times
Often we are given the time taken by a worker to finish a job alone.
If worker (A) takes (t_A) units of time to finish the job alone:
[
R_A = \frac{W}{t_A}
]
When only relative rates are needed (i.e., the job size (W) cancels out), we work with inverse times ( \frac{1}{t_A} ).
3.2 Combined Work of Two Workers
If worker (A) takes (t_A) units and worker (B) takes (t_B) units to finish the job alone, the combined time (t_{AB}) when they work together is: [ \frac{1}{t_{AB}} = \frac{1}{t_A} + \frac{1}{t_B} ] or [ t_{AB} = \frac{t_A t_B}{t_A + t_B} ] This is the harmonic mean of (t_A) and (t_B).
Why harmonic?
Because rates add linearly, but times are inverses of rates.
3.3 Generalization to (n) Workers
[ \frac{1}{t_{\text{joint}}} = \sum_{i=1}^{n} \frac{1}{t_i} ] where (t_i) is the time worker (i) takes alone.
4. Edge Cases & Counter‑Intuitive Situations
| Scenario | Analysis | Result |
|---|---|---|
| Zero workers | No rate (R=0). | Time (T = \frac{W}{0}) → *undefined/ |