Time & Work – Quick Study Notes
(For the Chhattisgarh Police Constable Exam – Quantitative Aptitude)
1. What is “Time & Work”?
- Time = How long it takes to finish a job.
- Work = The job itself.
- Work rate = How much of the job is finished in one unit of time (usually a day).
Analogy: Think of a painting job. A painter who can finish a wall in 4 days paints ¼ of the wall each day.
2. Key Idea
Every person (or machine, etc.) can be described by a rate of work.
If two or more people work together, their rates simply add up.
3. Simple Formula
| Symbol | Meaning | Formula |
|---|---|---|
| (R) | Rate of work (part of job per day) | (R = \dfrac{1}{T}) |
| (T) | Time to finish the whole job alone | (T = \dfrac{1}{R}) |
| (W) | Total work (usually taken as 1 whole job) | – |
| (R_{\text{total}}) | Combined rate of all workers | (R_{\text{total}} = R_1 + R_2 + \dots) |
| (T_{\text{total}}) | Time when all workers work together | (T_{\text{total}} = \dfrac{1}{R_{\text{total}}}) |
Remember:
- Work is always 1 job (you can think of it as “100% of the job”).
- Rates are fractions of the job per day.
4. Step‑by‑Step Approach
- Find each worker’s rate
- If a worker takes (t) days to finish the job, his rate = (1/t).
- Add the rates (when working together).
- Take the reciprocal of the total rate to get the combined time.
5. Tiny Example
Problem:
- Worker A finishes the job in 10 days.
- Worker B finishes the same job in 15 days.
- They work together. How many days will it take?
Solution:
| Worker | Time alone (days) | Rate (1/\text{days}) |
|---|---|---|
| A | 10 | (1/10 = 0.10) |
| B | 15 | (1/15 ≈ 0.0667) |
Add the rates:
(0.10 + 0.0667 = 0.1667) of the job per day.
Reciprocal → time together:
(T = 1 / 0.1667 ≈ 6) days.
So, A and B together finish the job in 6 days.
6. Quick Tips
| Situation | How to Solve |
|---|---|
| One worker’s time known, find rate | Rate = (1/\text{time}) |
| Two rates given, find combined time | Add rates → take reciprocal |
| Work done by a group in a given time | Work done = (total rate) × (time) |
| Missing worker’s time | Use (T = 1/(R_{\text{total}} - R_{\text{other}})) |
7. Practice Questions
- Simple – A can finish a task in 12 days. B can finish it in 18 days. Together, how many days?
- Mixed – If A and B together finish a job in 5 days, and A alone would take 20 days, how many days does B take alone?
- Real‑world – Three workers A, B, C can finish a road in 7, 10, and 14 days respectively. How long will they take if all three work together?
(Try solving before checking the answers in your study material.)
8. Summary
- Rate = portion of job finished per day.
- Work = 1 whole job.
- Time for a group = reciprocal of the sum of individual rates.
- Use short, clear steps: find rates → add → reciprocal → answer.
Keep practicing with small numbers; the pattern will become second nature!