Chhattisgarh Police Constable /Quantitative Aptitude

Time & work

Commercial Maths · free study notes

Time & Work – Quick Study Notes

(For the Chhattisgarh Police Constable Exam – Quantitative Aptitude)


1. What is “Time & Work”?

  • Time = How long it takes to finish a job.
  • Work = The job itself.
  • Work rate = How much of the job is finished in one unit of time (usually a day).
    Analogy: Think of a painting job. A painter who can finish a wall in 4 days paints ¼ of the wall each day.

2. Key Idea

Every person (or machine, etc.) can be described by a rate of work.
If two or more people work together, their rates simply add up.


3. Simple Formula

Symbol Meaning Formula
(R) Rate of work (part of job per day) (R = \dfrac{1}{T})
(T) Time to finish the whole job alone (T = \dfrac{1}{R})
(W) Total work (usually taken as 1 whole job) –
(R_{\text{total}}) Combined rate of all workers (R_{\text{total}} = R_1 + R_2 + \dots)
(T_{\text{total}}) Time when all workers work together (T_{\text{total}} = \dfrac{1}{R_{\text{total}}})

Remember:

  • Work is always 1 job (you can think of it as “100% of the job”).
  • Rates are fractions of the job per day.

4. Step‑by‑Step Approach

  1. Find each worker’s rate
    • If a worker takes (t) days to finish the job, his rate = (1/t).
  2. Add the rates (when working together).
  3. Take the reciprocal of the total rate to get the combined time.

5. Tiny Example

Problem:

  • Worker A finishes the job in 10 days.
  • Worker B finishes the same job in 15 days.
  • They work together. How many days will it take?

Solution:

Worker Time alone (days) Rate (1/\text{days})
A 10 (1/10 = 0.10)
B 15 (1/15 ≈ 0.0667)

Add the rates:
(0.10 + 0.0667 = 0.1667) of the job per day.

Reciprocal → time together:
(T = 1 / 0.1667 ≈ 6) days.

So, A and B together finish the job in 6 days.


6. Quick Tips

Situation How to Solve
One worker’s time known, find rate Rate = (1/\text{time})
Two rates given, find combined time Add rates → take reciprocal
Work done by a group in a given time Work done = (total rate) × (time)
Missing worker’s time Use (T = 1/(R_{\text{total}} - R_{\text{other}}))

7. Practice Questions

  1. Simple – A can finish a task in 12 days. B can finish it in 18 days. Together, how many days?
  2. Mixed – If A and B together finish a job in 5 days, and A alone would take 20 days, how many days does B take alone?
  3. Real‑world – Three workers A, B, C can finish a road in 7, 10, and 14 days respectively. How long will they take if all three work together?

(Try solving before checking the answers in your study material.)


8. Summary

  • Rate = portion of job finished per day.
  • Work = 1 whole job.
  • Time for a group = reciprocal of the sum of individual rates.
  • Use short, clear steps: find rates → add → reciprocal → answer.

Keep practicing with small numbers; the pattern will become second nature!