Time & Work – Assam Police Sub‑Inspector (SI) – Quantitative Aptitude
1. Simple Explanation
Time & Work problems ask you to find how long it takes, or how many people are required, when several workers (or machines) work together or separately.
- Work is the total job (e.g., building a wall).
- Rate (
W/T) is the amount of work done per unit time. - If two or more workers work together, their rates add.
- If a worker stops after a part of a job, the remaining work is handled by the remaining workers.
2. Key Points
| Concept | Symbol | Formula | Notes |
|---|---|---|---|
| Rate of a worker | r |
r = Work / Time |
Work is often taken as 1 unit. |
Work done in time t |
W |
W = r × t |
Use when only part of the job is done. |
| Combined rate | r_total |
r_total = r1 + r2 + … |
Sum of individual rates. |
| Time required for a job | T |
T = Work / r_total |
If all workers work together. |
| Work left after some time | W_left |
W_left = Work - r_total × t_done |
For partial work problems. |
| Work done by one worker after another leaves | W1 |
W1 = r1 × t1 |
t1 is the time that worker 1 worked. |
| Proportion of work | W1 : W2 |
r1 : r2 |
If two workers finish a job together, their rates are proportional to the work they do. |
| Conversion between units | – | Use consistent units (e.g., hours, days). | 1 day = 24 hrs, 1 hour = 60 min, etc. |
3. Worked Example
Problem
A, B and C can build a wall in 12, 15 and 20 days respectively.
A and B start together and after 5 days C joins them.
How many more days are required to finish the wall?
Step‑by‑Step
| Step | Calculation | Result |
|---|---|---|
| 1. Rate of A | r_A = 1 / 12 |
0.0833 wall/day |
| 2. Rate of B | r_B = 1 / 15 |
0.0667 wall/day |
| 3. Combined rate of A+B | r_AB = r_A + r_B = 0.15 |
0.15 wall/day |
| 4. Work done in first 5 days | W_done1 = r_AB × 5 = 0.75 |
75% of wall |
| 5. Work left | W_left = 1 – 0.75 = 0.25 |
25% of wall |
| 6. Rate of all three | r_total = r_A + r_B + r_C |
|
r_C = 1 / 20 = 0.05 |
0.15 + 0.05 = 0.20 wall/day |
|
| 7. Time to finish remaining work | t = W_left / r_total = 0.25 / 0.20 = 1.25 days |
1 day 6 hrs |
Answer: After C joins, the wall will be finished in 1 day 6 hours.
4. Quick Revision Summary
- Define the rate of each worker (
rate = 1 / time to finish job). - Add rates when workers work together.
- Calculate work done:
work = rate × time. - Subtract from total to find remaining work.
- Divide remaining work by combined rate to get the remaining time.
- Keep units consistent; convert as needed.
Tip: Draw a table for each worker (rate, time worked, work done) – it keeps the numbers organized and reduces errors.
Good luck with your preparation!