🏫 Assam TET – Quantitative Aptitude

Topic: Time & Work

Time & Work problems are a staple in TET exams.
They test your ability to apply simple algebra to real‑world scenarios involving labor, machines, or any entities that “work” over time.


📌 Simple Explanation

  • Work is the total amount of job that must be completed (e.g., painting a wall, building a bridge).
  • Rate of Work is how fast a person/ machine/ team can do the job, expressed as work per unit time (e.g., 1/5 of the job per hour).
  • Time is the duration needed to finish the job at a given rate.

Key formulae

Symbol Meaning Expression
(W) Total work –
(r) Rate of work (W) per unit time
(t) Time to finish –
Work done (W = r \times t)
Combined rate If two people work together, (r_{total} = r_1 + r_2)
Work done together (W = (r_1 + r_2) \times t)

All rates must be in the same units (e.g., per hour).


🔑 Key Points

  1. Convert units

    • Always express rates in the same unit (per hour, per day, etc.).
    • If a person can finish in 4 days, rate = (1/4) job per day.
  2. Working together or separately

    • For together: add rates.
    • For sequential tasks: sum times or use the appropriate formula.
  3. Work left after a certain time

    • Work done = rate × time.
    • Work left = total work – work done.
  4. Work by one after another

    • If (A) works for (x) hours, then (B) works for (y) hours, total work = (r_A x + r_B y).
  5. “X is Y times faster”

    • If (A) is 3 times faster than (B): (r_A = 3 r_B).
  6. Common pitfalls

    • Mixing up rate and time (e.g., dividing when you should multiply).
    • Forgetting to convert “days” to “hours” (or vice versa).
    • Not simplifying fractions before plugging into equations.

📐 Worked Example

Problem

A can paint a wall in 5 days. B can paint the same wall in 8 days.
They both start together and paint for 3 days. After that, only A continues.
How many more days will A need to finish the wall?


Solution Steps

  1. Find rates

    • (r_A = \frac{1}{5}) wall per day
    • (r_B = \frac{1}{8}) wall per day
  2. Combined rate (together)
    [ r_{AB} = r_A + r_B = \frac{1}{5} + \frac{1}{8} = \frac{8+5}{40} = \frac{13}{40}\ \text{wall/day} ]

  3. Work done in 3 days
    [ W_{\text{done}} = r_{AB} \times 3 = \frac{13}{40} \times 3 = \frac{39}{40}\ \text{wall} ]

  4. Work remaining
    [ W_{\text{left}} = 1 - \frac{39}{40} = \frac{1}{40}\ \text{wall} ]

  5. Time for A alone to finish remaining work
    [ t_A = \frac{W_{\text{left}}}{r_A} = \frac{\frac{1}{40}}{\frac{1}{5}} = \frac{1}{40} \times \frac{5}{1} = \frac{5}{40} = \frac{1}{8}\ \text{day} ]

  6. Convert to hours (if required)
    [ \frac{1}{8}\ \text{day} = 3\ \text{hours} ]


Answer

A needs 3 more hours (i.e., 1/8 day) to finish the wall.


📝 Quick Revision Summary

Concept Formula Example
Rate (r = \frac{1}{t}) A paints in 5 days → (r_A = 1/5)
Work done (W = r \times t) (W = (1/5+1/8) \times 3 = 39/40)
Combined rate (r_{tot} = r_1 + r_2) (r_{AB} = 1/5 + 1/8 = 13/40)
Remaining work (W_{\text{left}} = 1 - W_{\text{done}}) (1 - 39/40 = 1/40)
Time to finish (t = \frac{W_{\text{left}}}{r}) (t = \frac{1/40}{1/5} = 1/8) day
  • Tip: Always start by converting all times to the same unit, then write the “work” equation.
  • Tip: Check your answer by verifying that the sum of all work done equals 1 (the whole job).

Good luck with your Assam TET preparation! 🚀