🏫 Assam TET – Quantitative Aptitude
Topic: Time & Work
Time & Work problems are a staple in TET exams.
They test your ability to apply simple algebra to real‑world scenarios involving labor, machines, or any entities that “work” over time.
📌 Simple Explanation
- Work is the total amount of job that must be completed (e.g., painting a wall, building a bridge).
- Rate of Work is how fast a person/ machine/ team can do the job, expressed as work per unit time (e.g., 1/5 of the job per hour).
- Time is the duration needed to finish the job at a given rate.
Key formulae
| Symbol | Meaning | Expression |
|---|---|---|
| (W) | Total work | – |
| (r) | Rate of work | (W) per unit time |
| (t) | Time to finish | – |
| Work done | (W = r \times t) | |
| Combined rate | If two people work together, (r_{total} = r_1 + r_2) | |
| Work done together | (W = (r_1 + r_2) \times t) |
All rates must be in the same units (e.g., per hour).
🔑 Key Points
-
Convert units
- Always express rates in the same unit (per hour, per day, etc.).
- If a person can finish in 4 days, rate = (1/4) job per day.
-
Working together or separately
- For together: add rates.
- For sequential tasks: sum times or use the appropriate formula.
-
Work left after a certain time
- Work done = rate × time.
- Work left = total work – work done.
-
Work by one after another
- If (A) works for (x) hours, then (B) works for (y) hours, total work = (r_A x + r_B y).
-
“X is Y times faster”
- If (A) is 3 times faster than (B): (r_A = 3 r_B).
-
Common pitfalls
- Mixing up rate and time (e.g., dividing when you should multiply).
- Forgetting to convert “days” to “hours” (or vice versa).
- Not simplifying fractions before plugging into equations.
📐 Worked Example
Problem
A can paint a wall in 5 days. B can paint the same wall in 8 days.
They both start together and paint for 3 days. After that, only A continues.
How many more days will A need to finish the wall?
Solution Steps
-
Find rates
- (r_A = \frac{1}{5}) wall per day
- (r_B = \frac{1}{8}) wall per day
-
Combined rate (together)
[ r_{AB} = r_A + r_B = \frac{1}{5} + \frac{1}{8} = \frac{8+5}{40} = \frac{13}{40}\ \text{wall/day} ] -
Work done in 3 days
[ W_{\text{done}} = r_{AB} \times 3 = \frac{13}{40} \times 3 = \frac{39}{40}\ \text{wall} ] -
Work remaining
[ W_{\text{left}} = 1 - \frac{39}{40} = \frac{1}{40}\ \text{wall} ] -
Time for A alone to finish remaining work
[ t_A = \frac{W_{\text{left}}}{r_A} = \frac{\frac{1}{40}}{\frac{1}{5}} = \frac{1}{40} \times \frac{5}{1} = \frac{5}{40} = \frac{1}{8}\ \text{day} ] -
Convert to hours (if required)
[ \frac{1}{8}\ \text{day} = 3\ \text{hours} ]
Answer
A needs 3 more hours (i.e., 1/8 day) to finish the wall.
📝 Quick Revision Summary
| Concept | Formula | Example |
|---|---|---|
| Rate | (r = \frac{1}{t}) | A paints in 5 days → (r_A = 1/5) |
| Work done | (W = r \times t) | (W = (1/5+1/8) \times 3 = 39/40) |
| Combined rate | (r_{tot} = r_1 + r_2) | (r_{AB} = 1/5 + 1/8 = 13/40) |
| Remaining work | (W_{\text{left}} = 1 - W_{\text{done}}) | (1 - 39/40 = 1/40) |
| Time to finish | (t = \frac{W_{\text{left}}}{r}) | (t = \frac{1/40}{1/5} = 1/8) day |
- Tip: Always start by converting all times to the same unit, then write the “work” equation.
- Tip: Check your answer by verifying that the sum of all work done equals 1 (the whole job).
Good luck with your Assam TET preparation! 🚀