Time & Work – Study Notes
Target Audience: Jammu & Kashmir Police Constable (J&KPC)
Subject: Quantitative Aptitude
Topic: Time & Work
1. Simple Explanation
In a time & work problem, we are asked to find out how long (time) it takes for one or more workers (people, machines, etc.) to complete a given amount of work, or to determine how many workers are needed to finish a job in a specified time.
The fundamental relationship is:
[ \text{Work} = \text{Rate} \times \text{Time} ]
- Rate (or work per unit time) is how much of the job a worker can finish in one hour (or any chosen unit).
- Work is usually expressed in man‑hours or man‑days (i.e., the total amount of work that needs to be finished).
2. Key Points
| Concept | Formula | How to Use |
|---|---|---|
| Rate of one worker | ( r = \dfrac{1}{T} ) | (T) = time taken by worker alone to finish the whole job. |
| Combined rate of (n) workers | ( r_{\text{total}} = n \times r ) | If all workers work at the same rate. |
| Time to finish a job with (n) workers | ( T_{\text{total}} = \dfrac{T_{\text{alone}}}{n} ) | Use when all workers have the same efficiency. |
| Number of workers needed to finish in time (t) | ( n = \dfrac{T_{\text{alone}}}{t} ) | Rearranging the above formula. |
| Adding or removing workers | Adjust (n) accordingly; recompute (T_{\text{total}}). | |
| Partial work | Work done = Rate × Time; Remaining work = Total work – Work done. |
Common Tricks
- Convert all times to the same unit (e.g., hours) before calculations.
- Work in fractions (e.g., ( \frac{1}{4} ) of a job) to avoid decimals.
- Use “man‑hours”: If a worker works 8 hours a day, his rate per day is ( \frac{1}{T_{\text{days}}} \times 8 ) man‑hours.
3. Worked Example
Problem:
A team of 6 police constables can clear a protest area in 8 hours.
Another team of 4 constables joins them.
How long will it take for the 10 constables to clear the area?
Step-by-Step Solution
-
Find the total work (W).
Let the total job be 1 “unit” of work.
The rate of 6 constables together:
[ \text{Rate}_{6} = \frac{1}{8}\ \text{unit/hour} ] -
Determine the rate of one constable.
[ \text{Rate}{1} = \frac{\text{Rate}{6}}{6} = \frac{1}{48}\ \text{unit/hour} ] -
Compute the combined rate of 10 constables.
[ \text{Rate}_{10} = 10 \times \frac{1}{48} = \frac{10}{48} = \frac{5}{24}\ \text{unit/hour} ] -
Find the time required (T).
[ T = \frac{\text{Total Work}}{\text{Rate}_{10}} = \frac{1}{\frac{5}{24}} = \frac{24}{5} = 4.8\ \text{hours} ] -
Convert to hours and minutes.
(0.8\ \text{hour} = 0.8 \times 60 = 48) minutes.
Answer: 4 hours 48 minutes.
4. Quick Revision Summary
- Formula: ( \text{Work} = \text{Rate} \times \text{Time} )
- Rate of one worker: ( r = \frac{1}{T_{\text{alone}}} )
- Combined rate: ( r_{\text{total}} = n \times r )
- Time with (n) workers: ( T_{\text{total}} = \frac{T_{\text{alone}}}{n} )
- Workers needed for time (t): ( n = \frac{T_{\text{alone}}}{t} )
- Always use the same time unit.
- Check work done vs. remaining work if partial time is involved.
With these rules and formulas, you can solve any standard time & work question that appears in the J&KPC Quantitative Aptitude section. Happy studying!