Time & Work – Quantitative Aptitude
(Tripura Patwari / Lekhpal Exam – Quantitative Aptitude)
1. Simple Explanation
Time & work problems ask you to find the amount of work done, the time taken, or the number of workers required when the rates of work of the workers (or machines, etc.) are given.
- Rate of work – amount of work done in one unit of time (e.g., workers per hour).
- Work – the total amount of job to be done, usually expressed in man‑hours or man‑days.
- Time – the duration needed to finish the job.
The basic relation is
[ \text{Work} = \text{Rate} \times \text{Time} ]
or, equivalently,
[ \text{Rate} = \frac{\text{Work}}{\text{Time}} \quad\text{and}\quad \text{Time} = \frac{\text{Work}}{\text{Rate}} ]
When several workers work together, their rates add up.
When one worker works for part of the time and another for the rest, you add the parts of work done.
2. Key Points
| Concept | Formula | Example |
|---|---|---|
| Individual rate | ( r_i = \frac{1}{t_i} ) (if a worker completes the job alone in (t_i) hours) | Worker A finishes in 10 h → (r_A = 1/10) job per hour |
| Combined rate of (n) workers | ( r_{\text{total}} = \sum_{i=1}^{n} r_i ) | 3 workers with rates (1/6, 1/8, 1/10) → (r_{\text{total}} = 0.333…) |
| Time for combined work | ( t_{\text{total}} = \frac{1}{r_{\text{total}}} ) | (t = 1/0.333… = 3) h |
| Work done in part of time | ( W_{\text{part}} = r \times t_{\text{part}} ) | In 2 h, worker A does (2 \times 1/10 = 0.2) of job |
| Work remaining after partial work | ( W_{\text{rem}} = 1 - W_{\text{done}} ) | After 0.2 done, remaining 0.8 |
| Number of workers needed to finish remaining work in given time | ( n = \frac{W_{\text{rem}}}{r_{\text{worker}} \times t_{\text{given}}} ) | If 1 worker does 1/10 job per hour, to finish 0.8 job in 4 h need (n = 0.8/(0.1 \times 4) = 2) workers |
| Effect of idle time | If a worker works only part of the period, multiply his rate by the fraction of time worked | Worker works 3 h out of 8 h → effective rate (r \times \frac{3}{8}) |
| Changing effort vs. time | If two workers work together for (t_1) and then one leaves, the remaining worker continues alone | Compute combined work for (t_1), then remaining work for remaining time |
Helpful Tricks
- Work in “units” – Treat the whole job as 1 unit.
- Rate as “jobs per hour” – Easier to add than fractions of hours.
- Use “man‑hours” – If a worker’s rate is unknown, assume a worker does 1 job in 1 hour → rate = 1. Then scale.
- Cross‑multiplication – For “proportional” problems (e.g., “Worker A does 3× work of B”), set up a ratio.
3. Worked Example
Problem
3 workers – A, B, and C – can complete a project in 12 h, 15 h, and 20 h respectively, if they work alone.
They work together for 4 h. After that, worker C leaves, and A and B finish the remaining work.
How many hours do A and B take to finish the job after C leaves?
Step‑by‑step Solution
| Step | Calculation | Explanation |
|---|---|---|
| 1. Compute individual rates | (r_A = 1/12), (r_B = 1/15), (r_C = 1/20) | Job per hour |
| 2. Combined rate of all three | (r_{\text{all}} = 1/12 + 1/15 + 1/20 = 0.0833 + 0.0667 + 0.05 = 0.2) | Sum of rates |
| 3. Work done in first 4 h | (W_{\text{done}} = r_{\text{all}} \times 4 = 0.2 \times 4 = 0.8) | 80 % of job |
| 4. Work remaining | (W_{\text{rem}} = 1 - 0.8 = 0.2) | 20 % of job |
| 5. Combined rate of A and B | (r_{AB} = 1/12 + 1/15 = 0.0833 + 0.0667 = 0.15) | Sum of their rates |
| 6. Time needed by A and B to finish 0.2 job | (t_{AB} = \frac{W_{\text{rem}}}{r_{AB}} = \frac{0.2}{0.15} = \frac{4}{3} \approx 1.33) h | 1 h 20 min |
| Result | A and B take 1 h 20 min to finish the remaining work. |
4. Quick Revision Summary
- Rate = work completed in one hour.
- Work = rate × time.
- Combined rates add up; time for combined work is inverse of combined rate.
- Partial work: rate × part‑time; remaining work = 1 – work done.
- Number of workers: (n = \frac{\text{remaining work}}{(\text{rate per worker} \times \text{time available})}).