Time & Work – Meghalaya Forest Guard (Quantitative Aptitude)

Goal: Learn how to solve problems where several workers (or machines) perform a job together or separately, using the concept of rate of work and time.


1. Simple Explanation

  • Rate of work = amount of work done per unit time (e.g., jobs per hour).
  • If A can finish a job in T hours, his rate is R = 1/T jobs per hour.
  • When multiple workers work together, their rates add up.
  • To find total time: time = total work / combined rate.

2. Key Points

Concept Formula Example
Individual rate R = 1 / T A finishes in 8 h → R_A = 1/8 job/h
Combined rate R_total = R_A + R_B + … Two workers: R_total = R_A + R_B
Total work Usually 1 job (or 100 % of the job) 1 job = 100 %
Time to finish T = Total work / R_total T = 1 / R_total
Work done in time t W = R_total * t 0.5 job in 4 h → R_total = 0.125 job/h
If workers are added/removed Recalculate R_total accordingly
Equality of work If two workers do equal work, their rates are inversely proportional to their times.

3. Worked Example

Problem (typical for the Forest Guard exam):

Babu can clear a forest area in 12 days. Chandra can do the same in 15 days. They work together for 4 days and then Babu leaves. How many more days will Chandra need to finish the remaining work?

Step‑by‑step solution

  1. Find individual rates (jobs per day).

    • Babu: R_B = 1/12 job/day
    • Chandra: R_C = 1/15 job/day
  2. Combined rate when both work together.

    R_total = R_B + R_C = 1/12 + 1/15 = (5 + 4)/60 = 9/60 = 3/20 job/day

  3. Work done in the first 4 days.

    Work_done_4d = R_total * 4 = (3/20) * 4 = 12/20 = 3/5 of the job

  4. Remaining work.

    Remaining = 1 – 3/5 = 2/5 of the job

  5. Chandra works alone now.

    Her rate is 1/15 job/day.
    Time needed for remaining work:

    T_remaining = Remaining / R_C = (2/5) / (1/15) = (2/5) * 15 = 6 days

Answer

Chandra needs 6 more days to finish the forest clearing.


4. Quick Revision Summary

  • Rate = 1 / time.
  • Combined rate = sum of individual rates.
  • Time to finish = Total work / Combined rate.
  • For partial work: Work_done = Rate * time.
  • Always assume total work = 1 job unless stated otherwise.
  • Convert all units (hours, days, etc.) consistently.
  • Check for “equal work” scenarios: equal work → inverse time relationship.

Tip: Draw a simple table of times, rates, and work done; it keeps the algebra clean and reduces mistakes.