Time & Work – Study Notes

Quantitative Aptitude – Arunachal Pradesh Police Constable Exam


1. Simple Explanation

Time & Work deals with how long it takes people (or machines) to finish a job and how fast they work.

  • Work is the total job to be done (e.g., building a wall).
  • Rate of work is how much of the job one person can finish in a unit of time (often per day).
  • If two people work together, their rates add.
  • If one person works against another (e.g., painting a wall while the other is sanding), you subtract rates.

2. Key Points & Formulas

Concept Symbol Formula Meaning
Work done (W) (W = \text{Rate} \times \text{Time}) Total job completed
Rate of work (R) (R = \frac{W}{T}) Portion of job per unit time
Time taken (T) (T = \frac{W}{R}) Duration to finish the job
People working together (n) (R_{\text{total}} = \sum_{i=1}^n R_i) Sum of individual rates
One works against another (R_{\text{net}} = R_{\text{good}} - R_{\text{bad}}) Net progress per unit time
Work left after (k) days (W_{\text{left}} = W - k(R_{\text{total}})) Remaining job
Work done by (k) workers in (t) days (W = k \times R \times t) When all workers are equal
Work done by a person in (t) days (W = R \times t) For a single worker

Special Cases

  1. Work done by one person after another leaves work

    • If A does 1/3 of work in 2 days, A’s rate = ( \frac{1/3}{2} = \frac{1}{6}) job/day.
    • If B does 1/4 of work in 3 days, B’s rate = ( \frac{1/4}{3} = \frac{1}{12}) job/day.
    • Together, rate = ( \frac{1}{6} + \frac{1}{12} = \frac{1}{4}) job/day → 4 days to finish.
  2. Work done by a person in (t) days

    • If one person finishes a job in (x) days, his rate = ( \frac{1}{x}) job/day.
    • The same job takes (x \times t) days for (t) people working at the same rate.
  3. Work left after (t) days

    • If work rate = (R) and time used = (t), then work done = (R \times t).
    • Work left = (1 - R\times t) (if total work = 1 job).

3. Worked Example

Problem

Three workers, A, B, and C, can complete a road in 12, 15, and 18 days respectively.
If A and B work together for 3 days, then C joins them.
How many more days are required for all three to finish the road?

Step‑by‑Step Solution

  1. Calculate individual rates.

    • A’s rate (R_A = \frac{1}{12}) road/day.
    • B’s rate (R_B = \frac{1}{15}) road/day.
    • C’s rate (R_C = \frac{1}{18}) road/day.
  2. Work done by A and B in 3 days.
    [ W_{\text{AB}} = (R_A + R_B) \times 3 = \left(\frac{1}{12} + \frac{1}{15}\right) \times 3 ] Find common denominator 60:
    [ \frac{1}{12} = \frac{5}{60},; \frac{1}{15} = \frac{4}{60}; \Rightarrow; R_{\text{AB}} = \frac{9}{60} = \frac{3}{20} ] [ W_{\text{AB}} = \frac{3}{20} \times 3 = \frac{9}{20} = 0.45 \text{ of the road} ]

  3. Work remaining after 3 days.
    [ W_{\text{left}} = 1 - 0.45 = 0.55 ]

  4. Rate when all three work together.
    [ R_{\text{total}} = R_A + R_B + R_C = \frac{1}{12} + \frac{1}{15} + \frac{1}{18} ] Common denominator 180:
    [ \frac{1}{12} = \frac{15}{180},; \frac{1}{15} = \frac{12}{180},; \frac{1}{18} = \frac{10}{180} ] [ R_{\text{total}} = \frac{15+12+10}{180} = \frac{37}{180} \approx 0.2056 \text{ road/day} ]

  5. Time needed for the remaining 0.55 of the road.
    [ t = \frac{W_{\text{left}}}{R_{\text{total}}} = \frac{0.55}{37/180} = 0.55 \times \frac{180}{37} ] Compute: [ 0.55 \times 180 = 99,; \frac{99}{37} \approx 2.6757 \text{ days} ]