ATMA /Quantitative Ability

Time & work

Arithmetic · free study notes · Updated

Time & Work – Quantitative Ability

Program: ATMA
Subject: Quantitative Ability
Topic: Time & Work


📌 Simple Explanation

In “time & work” problems we treat work as a quantity that can be split into pieces and measured by how many people (or machines, etc.) can finish it in a given time.

  • Rate of work = amount of work done per unit time.
  • Work is usually expressed in units (e.g., “one job”, “100 units of work”).
  • If a person/thing can finish a job in T hours, their rate is 1/T units per hour.

When multiple workers cooperate or work in stages, we add or subtract their rates, or use the combined rate formula.


📚 Key Points & Formulas

Concept Formula Meaning
Rate of one worker r = 1 / T Units of work per hour
Combined rate (workers working together) r_total = r1 + r2 + … + rn Sum of individual rates
Time to finish a job together T_total = 1 / r_total Hours needed for all workers
Work done by a worker in t hours W = r * t Units of work completed
Work left after t hours W_left = Total - W_done
Work done by different workers in stages Sum of each worker’s contribution
One worker’s time when another works partially T1 = T2 * (r2 / r1) Derived from rate × time relationship
If one worker works 1/3 of the time T_total = T1 + (1/3)T1 + (2/3)T2 Example of partial work
Work rate of machines/people rate = 1 / time Often used for machines, engines, etc.

Important Rules

  1. Always convert rates to the same unit (e.g., hours).
  2. Add rates when workers work simultaneously.
  3. Subtract rates when a worker works against another (rarely in standard tests).
  4. Work left after a stage = Total work – Work done.
  5. Time = Work / Rate – never mix units.

🧮 Worked Example

Problem
A and B can complete a job in 20 hours and 30 hours respectively.
A works alone for 4 hours, then leaves.
B then works alone until the job is finished.
Find the total time taken to finish the job.

Step‑by‑Step

Step Calculation Result
1. Compute individual rates (r_A = \frac{1}{20}) units/hr, (r_B = \frac{1}{30}) units/hr (r_A = 0.05), (r_B = 0.0333...)
2. Work done by A in 4 hrs (W_A = r_A \times 4 = 0.05 \times 4 = 0.20) units 20% of the job
3. Work left after A’s part (W_{\text{left}} = 1 - 0.20 = 0.80) units 80% of the job
4. Time for B to finish remaining work (t_B = \frac{W_{\text{left}}}{r_B} = \frac{0.80}{0.0333...} \approx 24) hrs
5. Total time (T_{\text{total}} = 4 + 24 = 28) hrs

Answer: The job is finished in 28 hours.


🔍 Quick Revision Summary

Topic Recall
Rate of work rate = 1 / time_to_finish
Combined rate Sum of individual rates when working together
Time to finish time = 1 / combined_rate
Partial work Compute work done in a phase, subtract from total, then find time with remaining worker’s rate
Key formula ( \text{Work} = \text{Rate} \times \text{Time} )
Common pattern “X works Y hours, then Z works until job finishes” → split into phases
Units consistency Always use hours for time, units of work as whole job = 1
Check After solving, verify by multiplying the final time by combined rate to get 1 (whole job)

Quick Practice Question:
A can finish a job in 15 hrs, B in 25 hrs. A works alone for 3 hrs, then leaves. How long will B take to finish the remaining work?

Hint: Compute A’s rate, work done, remaining work, then divide by B’s rate.