Capital Budgeting – Study Notes
Program: CS Executive – Economics & Finance
1. Simple Explanation
Capital budgeting is the process by which a company decides whether to invest in a long‑term project (e.g., new plant, equipment, product line).
The goal: maximize shareholder wealth by selecting projects that generate the greatest net present value (NPV) while meeting risk and return criteria.
2. Key Points
| Topic | What It Means | Why It Matters |
|---|---|---|
| Cash‑Flow Focus | Uses project cash flows (inflows/outflows) rather than accounting profit. | Reflects real value creation. |
| Time Value of Money | Future cash flows discounted to present value using a required rate of return (discount rate). | Money today is worth more than money later. |
| Evaluation Techniques | • Net Present Value (NPV) – most widely used. • Internal Rate of Return (IRR). • Pay‑back Period (simple, ignores time value). • Discounted Pay‑back. • Profitability Index (PI). |
Provide different lenses; NPV is the gold‑standard. |
| Discount Rate | Often the company’s weighted average cost of capital (WACC), or a project‑specific hurdle rate. | Captures cost of funds & risk. |
| Risk & Sensitivity | Projects are uncertain; use scenario analysis, Monte‑Carlo simulation, or real‑options thinking. | Helps guard against over‑optimistic assumptions. |
| Capital Structure | Debt vs equity financing affects WACC & risk. | Determines appropriate discount rate. |
| Capital Budgeting Cycle | 1. Identify opportunity 2. Forecast cash flows 3. Select discount rate 4. Compute NPV/IRR 5. Decide 6. Monitor & review |
Ensures systematic, repeatable decision‑making. |
| Limitations | • Requires accurate forecasting. • Ignores opportunity cost of capital if not properly set. • Corporate culture & strategic fit may override NPV. |
Keep in mind when interpreting results. |
3. Worked Example
Problem
A firm is considering a new production line that costs $1,200,000 today (Year 0).
Projected operating cash flows:
| Year | Cash Flow (USD) |
|---|---|
| 1 | 300,000 |
| 2 | 350,000 |
| 3 | 400,000 |
| 4 | 450,000 |
| 5 | 500,000 |
- The firm’s WACC (discount rate) is 10 %.
- The project has no salvage value.
Question: Should the firm invest? Compute NPV, IRR, Pay‑back, and PI.
Step‑by‑Step
| Step | Calculation | Result |
|---|---|---|
| 1. Discount Factor | ( (1+0.10)^t ) | See below |
| 2. Present Value (PV) of CFs | ( PV_t = CF_t / (1+0.10)^t ) | |
| 3. NPV | ( \sum PV_t - Initial:Investment ) | |
| 4. IRR | Solve ( 0 = -1,200,000 + \sum \frac{CF_t}{(1+IRR)^t} ) | |
| 5. Pay‑back | Cumulative CF until > 0 | |
| 6. PI | ( \frac{\sum PV_t}{Initial:Investment} ) |
3.1 Compute PVs
| Year | CF | Discount Factor | PV |
|---|---|---|---|
| 0 | -1,200,000 | 1 | -1,200,000 |
| 1 | 300,000 | 1/1.10 = 0.9091 | 272,727 |
| 2 | 350,000 | 1/1.21 = 0.8264 | 289,644 |
| 3 | 400,000 | 1/1.331 = 0.7513 | 300,520 |
| 4 | 450,000 | 1/1.4641 = 0.6830 | 307,350 |
| 5 | 500,000 | 1/1.6105 = 0.6209 | 310,450 |
| Total PV | 1,481,591 |
3.2 NPV
[ NPV = 1,481,591 - 1,200,000 = $281,591 ]
Positive NPV → project adds value.
3.3 IRR
Solve the equation or use Excel’s IRR function.
Result: ≈ 14.8 %.
IRR > WACC (10 %) → acceptable.
3.4 Pay‑back Period
Cumulative CFs:
| Year | Cumulative CF |
|---|---|
| 0 | -1,200,000 |
| 1 | -900,000 |
| 2 | -550,000 |
| 3 | -150,000 |
| 4 | +157,350 |
Pay‑back occurs sometime in Year 4.
Exact:
[
\text{Payback} = 3 + \frac{150,000}{450,000} \approx 3.33\text{ years}
]
3.5 Profitability Index
[ PI = \frac{1,481,591}{1,200,000} = 1.236 (>1) ]
PI > 1 → project worthwhile.
Decision
All key metrics (NPV > 0, IRR > WACC, PI > 1, Pay‑back < 5 years) support investment.
4. Quick Revision Summary
- Capital budgeting = selecting long‑term projects to maximize shareholder wealth.
- Main goal: Positive NPV; IRR > hurdle rate; PI