Capital Budgeting – Study Notes

(CS Professional – Economics & Finance)


1. Simple Explanation

Capital budgeting is the process of evaluating and selecting long‑term investment projects (e.g., plant expansion, equipment purchase, new product lines). The goal is to decide which projects will generate sufficient future cash flows to justify the initial outlay and to add value to the firm.

Bottom line: A project is accepted if it increases shareholders’ wealth (usually measured by Net Present Value, NPV > 0).


2. Key Points

Concept What it is Why it matters
Net Present Value (NPV) Sum of discounted future cash flows minus initial cost. Positive NPV → value added.
Internal Rate of Return (IRR) Discount rate that makes NPV = 0. Shows the project’s return; compare with required rate of return (WACC).
Payback Period Time to recover initial investment. Simple liquidity measure (ignores time value of money).
Profitability Index (PI) NPV ÷ Initial Cost. Rank projects when capital is limited.
Weighted Average Cost of Capital (WACC) Firm’s cost of equity & debt weighted by capital structure. Required discount rate for NPV.
Capital Expenditure (CapEx) Initial outlay for assets. Must be financed (debt/equity).
Operating Cash Flow (OCF) Cash inflows from operations after taxes and working‑capital changes. Drives NPV calculation.
Depreciation & Tax Shield Non‑cash expense reducing taxable income. Increases cash flow.
Risk & Sensitivity Analysis Vary key assumptions (cash flow, discount rate). Tests robustness of decision.
Scenario & Monte‑Carlo Simulation Probabilistic modeling of uncertainty. Provides probability distribution of NPV.

3. Capital‑Budgeting Process (Step‑by‑Step)

  1. Identify Projects – Generate ideas, screen for feasibility.
  2. Estimate Cash Flows –
    • Initial CapEx (negative cash flow).
    • Annual operating cash flows (revenue – operating costs – taxes + depreciation tax shield).
    • Terminal cash flow (salvage value + working‑capital release).
  3. Determine Discount Rate –
    • Usually the firm’s WACC.
    • Adjust for project‑specific risk (use risk‑adjusted discount rate).
  4. Compute NPV & IRR – Use formulas below.
  5. Apply Decision Rules –
    • Accept if NPV > 0.
    • Accept if IRR ≥ WACC.
    • Prefer projects with higher PI when capital is constrained.
  6. Conduct Sensitivity/Scenario Analysis – Vary key inputs.
  7. Make Final Decision – Consider strategic fit, risk, resource constraints.
  8. Monitor & Evaluate – Track actual vs. projected cash flows.

4. Formulas

Symbol Formula Interpretation
NPV (\displaystyle NPV = \sum_{t=0}^{n}\frac{CF_t}{(1+r)^t}) Present value of all cash flows
IRR Solve (NPV = 0) for (r) Yield of the project
Payback Smallest (t) where (\sum_{i=1}^{t} CF_i \geq \text{CapEx}) Years to recover initial investment
PI (\displaystyle PI = \frac{NPV + \text{CapEx}}{\text{CapEx}}) Value created per dollar invested
WACC (\displaystyle WACC = \frac{E}{V}r_E + \frac{D}{V}r_D(1-T)) Weighted cost of capital

(E) = market value of equity, (D) = market value of debt, (V = E + D), (r_E) = cost of equity, (r_D) = cost of debt, (T) = corporate tax rate.


5. Worked Example

Project Details

Item Amount (USD)
Initial CapEx –$500,000
Annual operating cash flow (Years 1‑5) $120,000
Salvage value (Year 5) $80,000
WACC (discount rate) 10 %
Tax rate 30 %
Depreciation (straight‑line over 5 yrs) $100,000 per year

Step 1: Cash Flow Construction

Year Operating CF Depreciation Taxable Income Tax (30 %) Net Income Cash Flow (add back Dep.)
0 – 0 – 0 – –$500,000 (CapEx)
1 120,000 100,000 20,000 6,000 14,000 114,000
2 120,000 100,000 20,000 6,000 14,000 114,000
3 120,000 100,000 20,000 6,000 14,000 114,000
4 120,000 100,000 20,000 6,000 14,000 114,000
5 120,000 100,000 20,000 6,000 14,000 114,000 + 80,000 (salvage) = 194,000

Step 2: NPV Calculation

[ NPV = \sum_{t