1. Simple Explanation

Time & Work is a classic topic that deals with how long it takes for a person or a group of people (or machines) to finish a job, and how many people (or machines) are needed to finish a job in a given time.

  • Work is the total amount of job that needs to be done.
  • Rate (or Productivity) of a worker = work completed per unit time (e.g., per day).
  • Time = how long it takes to finish a job.

The fundamental relationship is

[ \text{Work} = \text{Rate} \times \text{Time} ]

When several workers work together, their rates add up.


2. Key Points & Formulas

Concept Symbol Formula Explanation
Rate of a worker (r) (r = \frac{1}{T}) If a worker completes the whole job in (T) days, his rate is (1/T) job/day.
Work done by a worker (W) (W = r \times t) Amount of work completed in (t) days.
Combined rate of (n) workers (R) (R = \sum r_i) Sum of individual rates.
Time to finish a job (T) (T = \frac{W}{R}) Total work divided by combined rate.
Work completed in part of a job (W_{\text{part}}) (W_{\text{part}} = r \times t) Used when a worker works for only part of the job.
Work remaining after (k) days (W_{\text{rem}}) (W_{\text{rem}} = W - r_k \times k) Subtract work done in (k) days.
Increase / Decrease in rate – – Use percentages: (r_{\text{new}} = r_{\text{old}} \times (1 \pm %)).
Work done by two workers in the same time – (r_A + r_B = \frac{1}{T_{\text{both}}}) If they finish together in (T_{\text{both}}) days.

Important Rules

  1. Adding Rates – When workers work together, add their rates to get the combined rate.
  2. Subtracting Rates – When one worker leaves, subtract his rate from the combined rate.
  3. Work in Parts – A job can be divided into parts (e.g., 1/3, 2/3). Compute work done in each part separately.
  4. Unit Consistency – Keep the same time unit (days, hours, etc.) across the problem.
  5. Work = Rate × Time – This is the core equation; rearrange it for any missing variable.

3. Worked Example

Problem

A piece of land is to be cleared.

  • Worker A alone can clear the land in 12 days.
  • Worker B alone can clear the land in 18 days.
  • Worker A works for 4 days, then B joins him.
  • After 3 more days of joint work, the land is completely cleared.
    Find the number of days B worked alone.

Step‑by‑Step Solution

Step What to find Calculation Result
1. Individual rates Rate of A and B (r_A = \frac{1}{12}) job/day, (r_B = \frac{1}{18}) job/day –
2. Work done by A alone (first 4 days) (W_{A,4}) (W_{A,4} = r_A \times 4 = \frac{1}{12}\times4 = \frac{1}{3}) job 1/3 of land
3. Remaining work (W_{\text{rem}}) (W_{\text{rem}} = 1 - \frac{1}{3} = \frac{2}{3}) job –
4. Combined rate of A and B (R_{AB}) (R_{AB} = r_A + r_B = \frac{1}{12} + \frac{1}{18} = \frac{5}{36}) job/day –
5. Time needed to finish remaining work (t_{\text{joint}}) (t_{\text{joint}} = \frac{W_{\text{rem}}}{R_{AB}} = \frac{\frac{2}{3}}{\frac{5}{36}} = \frac{2}{3}\times\frac{36}{5} = \frac{24}{5} = 4.8) days 4.8 days
6. Given joint time Check Problem says 3 days of joint work → contradiction? Re‑check: Problem states “After 3 more days of joint work” → So (t_{\text{joint}} = 3) days.
Hence compute number of days B worked alone (the remaining time after A’s 4 days and joint 3 days).
7. Work done in 3 days of joint work (W_{\text{joint}}) (W_{\text{joint}} = R_{AB}\times3 = \frac{5}{36}\times3 = \frac{5}{12}) job 5/12 of land
8. Total work done (W_{\text{done}}) (W_{\text{done}} = W_{A,4} + W_{\text{joint}} = \frac{1}{3} + \frac{5}{12} = \frac{4}{12} + \frac{5}{12} = \frac{9}{12} = \frac{3}{4}) job 3/4 of land
9. Remaining work (W_{\text{rem}})

Your note