Time & work

Commercial Maths · free study notes

Time & Work – Quick & Easy Study Notes


1. What is “Work”?

  • Work = the whole job you want finished.
    Example: 1 whole wall, 1 whole bucket of paint, 1 whole cake.

2. Key Ideas (in plain words)

Idea What it means Everyday picture
Rate How much of the job one person does per unit of time (e.g., per hour). A runner who can fill a bucket 1 / 2 hour.
Time How long it takes someone to finish the whole job. How long it takes to paint a wall.
Work The job itself, usually counted as “1 whole job”. One finished painting job.

Formulae (but think of them as simple statements)

  • Rate = Work ÷ Time
  • Time = Work ÷ Rate
  • Work = Rate × Time

You can rearrange them depending on what you know.


3. Work Done by Several People

When two (or more) people work together, their rates add:

Rate of A + Rate of B = Combined rate

Why?
Each person does a part of the job. Add the parts → total job done per hour.


4. Step‑by‑Step Guide

  1. Decide what you know – time, rate, or work.
  2. Write the missing value using one of the formulas.
  3. Add rates if more than one person is working.
  4. Plug numbers and solve.
  5. Check the answer – does it make sense? (e.g., time can’t be negative).

5. Tiny Example

Problem:

  • Person A finishes a job in 4 hours.
  • Person B finishes the same job in 6 hours.
  • How long will they take together?
Person Rate (job per hour)
A 1 ÷ 4 = 0.25
B 1 ÷ 6 ≈ 0.1667

Combined rate:
0.25 + 0.1667 = 0.4167 job per hour

Time together:
Time = 1 ÷ 0.4167 ≈ 2.4 hours (≈ 2 h 24 min)


6. Quick Practice Problems

# Problem Hint
1 A can paint a wall in 5 h. B can paint the same wall in 8 h. Together how long? Add rates.
2 A, B, and C finish a task in 10 h together. If A alone takes 15 h and B alone takes 20 h, how long does C take? Use RateA + RateB + RateC = 1/10.
3 A works for 3 h, then leaves. B takes over and finishes the job in 5 h. If A would finish the job alone in 9 h, how long does B take alone? Work done by A = RateA × 3.

7. Tips for Oracle Certification

  • Read the problem carefully – look for words like “together”, “alone”, “after”.
  • Convert all times to the same unit (hours, minutes, etc.) before calculating.
  • Keep the final answer in the same unit as the question asks.
  • Double‑check that you didn’t mix up “time” and “rate”.

Quick Summary

  • Rate = how fast someone works.
  • Time = how long it takes to finish.
  • Work = the whole job (usually 1).
  • Add rates when people work together.
  • Use the simple equations above to swap between rate, time, and work.

Happy studying – you’ve got this!