📚 Time & Work – Comprehensive Study Notes
For IIT‑JEE / Competitive Exams (Oracle Certification – Quantitative Aptitude)
1️⃣ Introduction
Time & Work problems are classic in quantitative aptitude.
They test your ability to translate a word‑problem into algebraic form and apply simple “rate” concepts.Key Idea: Work is the product of rate (how fast something is done) and time (how long it takes).
Notation
- (W) : Total amount of work (often in “man‑days” or “machine‑hours”)
- (R) : Rate of a worker/machine (units of work per unit time)
- (T) : Time taken (units of time)
2️⃣ Fundamental Formulae
| Concept | Formula | Explanation |
|---|---|---|
| Work done | (W = R \times T) | Total work equals rate multiplied by time. |
| Rate of a worker | (R = \dfrac{W}{T}) | Work per unit time. |
| Combined rate (parallel work) | (R_{\text{total}} = R_1 + R_2 + \dots + R_n) | When all workers/machines work together. |
| Time for combined work | (T = \dfrac{W}{R_{\text{total}}}) | Inverse of combined rate. |
| Work by a subset | (W_{\text{subset}} = R_{\text{subset}} \times T) | Work performed by a particular group or time interval. |
| Rate after a change | (R_{\text{new}} = R_{\text{old}} \pm \Delta R) | Adjust rate when someone joins/leaves or machinery fails. |
| Work remaining | (W_{\text{rem}} = W_{\text{total}} - W_{\text{done}}) | What is left to finish. |
| Work done in n days | (W_n = R \times n) | Useful for “in 10 days” or “in 5 days” questions. |
Tip: Always keep units consistent. If (R) is in man‑days per day (i.e., “man‑day” is the unit of work), then (T) must be in days.
3️⃣ Common Problem Types & Strategies
| Problem Type | Typical Question | Strategy |
|---|---|---|
| All work together | “Three workers A, B, C can finish a job in 12, 15, 20 days respectively. How long will they take together?” | Find individual rates: (\frac{1}{12}, \frac{1}{15}, \frac{1}{20}). Sum rates → total rate. Invert to get time. |
| Work done by one then the other | “A finishes 1/3 of the work in 5 days. B finishes the rest in 12 days. Find the ratio of their rates.” | Use (W_{\text{total}} = 1). Compute (R_A = \frac{1/3}{5}). Compute (R_B = \frac{2/3}{12}). Ratio (R_A : R_B). |
| Work after a change | “A can finish a job in 20 days. After 5 days, B joins and they finish in 10 more days. Find B’s rate.” | Compute work done by A in 5 days. Subtract from total. Remaining work done by both in 10 days → set up equation for B’s rate. |
| Work with machines | “One machine can do a job in 8 days. Another machine works at 70% of the first. The combined time is 4 days. How many machines are needed?” | Translate “70% of the first” to rate. Use combined rate to determine total machines. |
| Work with failure / stoppage | “A machine runs 8 hours a day but breaks down for 2 hours each day. Its effective working time is 6 hours/day.” | Treat effective working hours as time. Compute rate accordingly. |
| Work with fractions of work | “A does 1/5 of work in 4 days. B does the rest in 6 days.” | Compute rates using fractions directly. |
4️⃣ Derivation of Combined Rate (Illustrative)
Let
- Worker 1 completes the job in (t_1) days → Rate (R_1 = \frac{1}{t_1}).
- Worker 2 completes the job in (t_2) days → Rate (R_2 = \frac{1}{t_2}).
If they work together for (T) days, the total work done is
[ W_{\text{done}} = R_1 T + R_2 T = (R_1 + R_2)T. ]
But the total job is 1 unit of work, so
[ (R_1 + R_2)T = 1 \quad\Rightarrow\quad T = \frac{1}{R_1 + R_2}. ]
This simple derivation generalises to any number of workers or machines.
5️⃣ Tricky Points & Pitfalls
| Pitfall | Why it happens | How to avoid |
|---|---|---|
| Confusing “time” with “rate” | Some problems give “time to finish” while others give “rate of work”. | Keep the |