Time & Work – Study Notes
(For Andhra Pradesh Police Sub‑Inspector Exam – Quantitative Aptitude)
1. Simple Explanation
Time & Work problems relate the quantity of work done to the time and rate of work of one or more workers (or machines).
- Work (W): Total amount that must be completed (e.g., one job, one plot, one unit of material).
- Rate (R): Work done per unit of time (e.g., jobs per hour).
- Time (T): Duration taken to finish the work.
The fundamental relationship is
[ \boxed{W = R \times T} ]
From this we can derive:
- (R = \dfrac{W}{T}) – rate of a worker/machine.
- (T = \dfrac{W}{R}) – time required by a worker/machine.
When several workers work together, their rates add up.
2. Key Points & Useful Formulas
| Concept | Formula | Description |
|---|---|---|
| Single worker | (T = \dfrac{W}{R}) | Time needed by one worker to finish the whole work. |
| Two workers together | (R_{12} = R_1 + R_2) | Combined rate of workers 1 and 2. |
| Work done in a given time | (W_{done} = R \times T) | Portion of work completed by a worker in time (T). |
| Remaining work | (W_{rem} = W - W_{done}) | Work left after some portion is finished. |
| Work done by one after another | If worker A works for (t_a) and then B works for (t_b): (W = R_A t_a + R_B t_b) |
Sum of work done by each worker. |
| Speed of work | (S = \frac{1}{T}) (jobs per hour) | Often used when the total work (W = 1) job. |
| Work in days and hours | Convert units appropriately (e.g., 5 h = 5/24 days). | Be careful with units. |
Special Cases
- One worker leaves halfway
- Suppose worker A works for (t) hours and then leaves; worker B takes the rest.
- (W = R_A t + R_B (T - t)).
- Work done by workers at different speeds
- If worker A does (p%) of the work in the same time as worker B, then (R_A = \frac{p}{100} R_T) where (R_T) is the total rate.
- Work done in a certain number of days
- If (n) workers finish a job in (d) days, the combined rate is (\frac{1}{d}) jobs/day.
- Adding or removing workers changes the time inversely.
3. Worked Example
Problem
Two machines, M1 and M2, can complete a batch of work in 8 days and 12 days respectively. They work together for 3 days. After that, M1 stops and M2 works alone for the remaining days. How many days were needed in total?
Step‑by‑step Solution
-
Convert to rates (work = 1 batch).
- Rate of M1: (R_1 = \frac{1 \text{ batch}}{8 \text{ days}} = \frac{1}{8}) batch/day.
- Rate of M2: (R_2 = \frac{1}{12}) batch/day.
-
Work done together for 3 days
- Combined rate: (R_{12} = R_1 + R_2 = \frac{1}{8} + \frac{1}{12} = \frac{3}{24} + \frac{2}{24} = \frac{5}{24}) batch/day.
- Work done in 3 days: (W_{12} = R_{12} \times 3 = \frac{5}{24} \times 3 = \frac{15}{24} = \frac{5}{8}) batch.
-
Work remaining after 3 days
- Total work = 1 batch.
- Remaining work: (W_{\text{rem}} = 1 - \frac{5}{8} = \frac{3}{8}) batch.
-
M2 works alone to finish the remaining work
- Time needed by M2: (T_{\text{M2}} = \frac{W_{\text{rem}}}{R_2} = \frac{\frac{3}{8}}{\frac{1}{12}} = \frac{3}{8} \times 12 = \frac{36}{8} = 4.5) days.
-
Total time
- (T_{\text{total}} = 3) days (together) + (4.5) days (M2 alone) = 7.5 days.
Answer: 7.5 days (or 7 days 12 hours).
4. Quick Revision Summary
| Concept | Formula | Typical Question Type |
|---|---|---|
| Work‑rate relation | (W = RT) | “If X does Y in Z days, what is his rate?” |
| Combined rate | (R_{total} = R_1+R_2+…) | “Two workers finish a job together in … days.” |
| Time for one worker | (T = \frac{W}{R}) | “How long will worker A take alone?” |
| Remaining work | (W_{rem |