Time & work

Commercial Maths · free study notes

Time & Work – Quick & Easy Notes

Why it matters
In the police exam you’ll see questions about how long it takes people (or machines) to finish a job together. Knowing the trick saves you time and math.


1. The Basic Idea

What you know What you can find
How long one person takes to finish a job How long two or more people together will take
How long two people together take How long one person would take
The job that’s done in a certain time The remaining job after a part is finished

Think of it like this:
If one man can paint a wall in 4 days, and another can paint the same wall in 8 days, together they paint it faster. They’re like two painters sharing the work.


2. The Key Formula – “Rate”

  • Work = total job
    (e.g., painting the whole wall)
  • Rate = how much work a person can do in one day
    (e.g., 1/4 of the wall per day)

So:

Work = Rate × Time

or

Rate = Work ÷ Time

Everyday analogy

  • Imagine a pizza that’s 1 whole.
    • Person A can eat 1/4 of it in a day.
    • Person B can eat 1/6 of it in a day.
      Their combined “rate” is 1/4 + 1/6 = 5/12 of a pizza per day.

3. Adding Rates (People Working Together)

  1. Find each person’s rate
    • Rate of A = 1 / (days A takes)
    • Rate of B = 1 / (days B takes)
  2. Add the rates
    • Combined Rate = RateA + RateB (+ RateC if more people)
  3. Find the time together
    • Time together = 1 ÷ Combined Rate

Tip: Work is always “1” (the whole job). So the combined rate tells you how many whole jobs they finish each day.


4. Solving a Typical Problem

Problem

A can clean a room in 5 days. B can clean the same room in 10 days.
How long will they take if they work together?

Step‑by‑step

Step What to do Numbers
1 Find A’s rate 1 job ÷ 5 days = 0.20 job/day
2 Find B’s rate 1 job ÷ 10 days = 0.10 job/day
3 Add the rates 0.20 + 0.10 = 0.30 job/day
4 Find combined time 1 ÷ 0.30 = 3.33 days (≈ 3 days 8 hours)

Answer: They finish the room in about 3.3 days.


5. When One Person Works First

If one person works alone for some time, then the rest join:

  1. Compute work done by the first person
    • WorkDone = Rate × TimeWorked
  2. Subtract from total to get remaining work
  3. Use the remaining work with the combined rate of the rest to find extra time

6. Quick Practice

Problem:
C can finish a task in 6 days. D can finish the same task in 12 days.
If they work together for 2 days, how many more days will they need to finish the job?

Solution (short)

  1. Rates
    • C: 1/6 job/day
    • D: 1/12 job/day
  2. Together’s rate
    • 1/6 + 1/12 = 1/4 job/day
  3. Work done in 2 days
    • 2 × 1/4 = 1/2 job
  4. Remaining work
    • 1 – 1/2 = 1/2 job
  5. Time needed for remaining
    • (1/2) ÷ (1/4) = 2 days

Answer: They need 2 more days.


7. Quick Reference Cheat‑Sheet

Symbol Meaning Example
W Total work (always 1 job) 1 wall
R Rate of a person 1/5 wall per day
T Time taken 5 days
Rate = W ÷ T T = W ÷ Rate
Combined Rate = sum of individual rates

8. Final Tips

  • Always start with 1 job – the whole task.
  • Convert all times to the same unit (days, hours, etc.).
  • Check your answer – the time together must be less than the fastest person alone.
  • Practice a few problems from past papers – the pattern is the same.

Good luck! Remember: treat each worker like a “pizza slice maker” – the more slices you have per day, the faster the pizza is finished.