Time & Work – Study Notes

(For Kerala Police Sub‑Inspector Examination – Quantitative Aptitude)


1. Simple Explanation

Time & Work problems ask you to find how long something will take to finish a job when one or more workers (or machines, etc.) are involved, or how many workers are needed to finish a job in a given time.

  • Work = amount of job (e.g., 1 whole job, 5 units).
  • Rate of Work = work done per unit time (e.g., 0.1 job per hour).
  • Work Done = Rate × Time.

When several workers work together, their rates add.
When they work alternately or at different times, the work is split accordingly.


2. Key Points & Formulas

Concept Symbol Formula Remark
Rate of a worker ( r ) ( r = \frac{\text{Work}}{\text{Time}} = \frac{1}{T} ) (if the whole job is 1 unit) Work done per hour
Combined rate (workers A & B) ( r_A + r_B ) ( \frac{1}{T_{AB}} = \frac{1}{T_A} + \frac{1}{T_B} ) Work rates add
Time to finish a job together ( T_{AB} ) ( T_{AB} = \frac{1}{\frac{1}{T_A} + \frac{1}{T_B}} ) Harmonic sum
Work done in a given time ( W ) ( W = r \times t ) ( r = \frac{1}{T} )
Number of workers for given time ( n ) ( n = \frac{1}{T_{\text{job}}} \div \frac{1}{T_{\text{worker}}} = \frac{T_{\text{worker}}}{T_{\text{job}}} ) If all workers identical
Alternate work – Sum the work of each worker for their working period Usually “A works 3 hours, B 2 hours, …”
Work done by a worker who didn’t finish – If ( r \times t < 1 ) then work left = ( 1 - r \times t )
Work done in days, hours, minutes – Convert all times to same unit (e.g., hours) before calculation

Common Pitfalls

  1. Mixing units – always convert to the same unit (hours, minutes).
  2. Assuming linearity incorrectly – rates add, times do not.
  3. Neglecting partial work – if a worker stops midway, compute remaining work separately.

3. Worked Example

Problem:
A and B can paint a wall in 12 hours and 18 hours respectively.
A works for 4 hours alone, then B joins.
How much more time will B need to finish the painting?

Step‑by‑Step Solution

Step Calculation Explanation
1. Find each worker’s rate ( r_A = \frac{1}{12} ) job/hr, ( r_B = \frac{1}{18} ) job/hr 1 job (full wall) / time taken
2. Work done by A in 4 hrs ( W_A = r_A \times 4 = \frac{1}{12}\times 4 = \frac{1}{3} ) job A paints one‑third of the wall
3. Remaining work ( W_{\text{rem}} = 1 - \frac{1}{3} = \frac{2}{3} ) job
4. Combined rate of A & B ( r_{AB} = r_A + r_B = \frac{1}{12} + \frac{1}{18} = \frac{5}{36} ) job/hr Add rates
5. Time to finish remaining work ( t_{\text{fin}} = \frac{W_{\text{rem}}}{r_{AB}} = \frac{2/3}{5/36} = \frac{2/3 \times 36}{5} = \frac{24}{5} = 4.8 ) hrs
6. Convert 0.8 hr to minutes (0.8 \times 60 = 48) min
Result 4 hours 48 minutes After A’s 4‑hour solo stint, B (with A) will finish the wall in 4 h 48 min.

Answer: 4 h 48 min


4. Quick Revision Summary

  • Rate: ( r = \frac{1}{T} ) (job per hour).
  • Combined rate: sum of individual rates.
  • Time together: ( T_{AB} = \frac{1}{\frac{1}{T_A} + \frac{1}{T_B}} ).
  • Work in time: ( W = r \times t ).
  • Workers needed: ( n = \frac{T_{\text{worker}}}{T_{\text{job}}} ).
  • Always use the same units (hours, minutes).
  • Check partial work – if a worker stops early, compute remaining job separately.
  • Common formulae to memorize
    • ( \frac{1}{T_{\text{total}}} = \sum \frac{1}{T_{\text{worker}}} )
    • ( \text{Time left} = \frac{\text{Remaining work}}{\text{Combined rate}} )

With these basics and the worked example as a template, you can tackle most “Time & Work” questions in the SI exam. Good luck!