Puducherry Police Sub-Inspector (SI) /Quantitative Aptitude

Time & work

Commercial Maths · free study notes · Updated

Time & Work – Quantitative Aptitude Notes

Program: Puducherry Police Sub‑Inspector (SI)
Exam: Quantitative Aptitude – “Time & Work”

Goal: Understand the core concepts, solve the most common problem types, and be able to revise quickly before the exam.


1. Simple Explanation

Concept What it Means Example
Work Total amount of job that needs to be completed. Usually measured in “man‑days” or “man‑hours”. Building a wall = 120 man‑days
Rate (Speed) How much work a person can finish in one unit of time. Denoted as R. A worker can finish 1/10 of the wall in a day → R = 1/10 days⁻¹
Time Duration needed to complete a task. Denoted as T. 5 days to finish the wall
Rate × Time = Work Fundamental relation: Work = Rate × Time. (1/10) × 5 = 1/2 wall → 0.5 of the wall done

2. Key Formulas & Relationships

Scenario Formula Intuition
Single worker T = W / R Time = Work ÷ Rate
Multiple workers together R_total = Σ R_i
T = W / R_total
Add individual rates (since they work simultaneously)
Work done in a given time Work_done = R × T Multiply rate by time
Work remaining Work_remaining = W – Work_done Subtract what’s already done
Work in terms of “man‑days” Man‑days = Number_of_workers × Time Equivalent to W = Σ (1 / R_i) × T when R_i = 1/Day for each worker
Faster worker If worker A is k times as fast as B ⇒ R_A = k × R_B Useful when converting rates

3. Common Problem Types

Problem Key Idea How to Approach
A & B together finish a job Combined rate = R_A + R_B T = W / (R_A+R_B)
A works alone for some time, then B joins Separate phases → add work done in each Work_A = R_A × t1
Work_B = R_B × t2
Work_total = Work_A + Work_B
One worker leaves Subtract his contribution from total work Work_remaining = W – R_left × t_left
Two workers work at different rates Use ratio of speeds R_A : R_B = 1 : 2 → R_A = 1/3, R_B = 2/3 (if total = 1/day)
Work done by one worker alone vs together Compare time taken T_A = W / R_A vs T_total = W / (R_A+R_B)
Work done in parts Break job into segments (e.g., 1st part by A, 2nd by B) Compute each part’s time separately

4. Worked Example

Problem

A and B can complete a piece of work in 12 days and 15 days respectively. If they work together for 4 days and then B leaves, how many more days will A need to finish the remaining work?

Step‑by‑Step Solution

Step Explanation Calculation
1. Find individual rates Rate = 1 / days per job R_A = 1/12
R_B = 1/15
2. Combined rate for first 4 days R_total = R_A + R_B R_total = 1/12 + 1/15 = 5/60 + 4/60 = 9/60 = 3/20
3. Work done in first 4 days Work_done = R_total × 4 Work_done = (3/20) × 4 = 12/20 = 3/5
4. Remaining work Work_remaining = 1 – Work_done Work_remaining = 1 – 3/5 = 2/5
5. Time for A alone T = Work_remaining / R_A T = (2/5) / (1/12) = (2/5) × 12 = 24/5 = 4.8 days

Answer: A needs 4.8 days (≈ 4 days 19 hours) to finish the remaining work.

Tip: Always convert rates to a common denominator first, then simplify.


5. Quick Revision Summary

  • Work = Rate × Time – the universal rule.
  • Rate of a worker is the part of the job he can finish in one day (or hour).
  • Combined rate = sum of individual rates when workers work together.
  • Time required = Work / Combined rate.
  • Common trick: Convert all rates to a common denominator (e.g., days⁻¹) before adding/subtracting.
  • When a worker leaves or joins, treat his contribution as a separate time segment.
  • Check units: If work is in “man‑days”, rate is in “work per day”; if time is in hours, convert rates accordingly.
  • Always verify the answer by plugging back into the equation: Rate × Time should equal the work (or the remaining work).

6. Quick Practice Questions (Try before the exam)

  1. **A can finish a job in 20