Time & Work – Quantitative Aptitude Notes
Program: Puducherry Police Sub‑Inspector (SI)
Exam: Quantitative Aptitude – “Time & Work”
Goal: Understand the core concepts, solve the most common problem types, and be able to revise quickly before the exam.
1. Simple Explanation
| Concept | What it Means | Example |
|---|---|---|
| Work | Total amount of job that needs to be completed. Usually measured in “man‑days” or “man‑hours”. | Building a wall = 120 man‑days |
| Rate (Speed) | How much work a person can finish in one unit of time. Denoted as R. | A worker can finish 1/10 of the wall in a day → R = 1/10 days⁻¹ |
| Time | Duration needed to complete a task. Denoted as T. | 5 days to finish the wall |
| Rate × Time = Work | Fundamental relation: Work = Rate × Time. |
(1/10) × 5 = 1/2 wall → 0.5 of the wall done |
2. Key Formulas & Relationships
| Scenario | Formula | Intuition |
|---|---|---|
| Single worker | T = W / R |
Time = Work ÷ Rate |
| Multiple workers together | R_total = Σ R_iT = W / R_total |
Add individual rates (since they work simultaneously) |
| Work done in a given time | Work_done = R × T |
Multiply rate by time |
| Work remaining | Work_remaining = W – Work_done |
Subtract what’s already done |
| Work in terms of “man‑days” | Man‑days = Number_of_workers × Time |
Equivalent to W = Σ (1 / R_i) × T when R_i = 1/Day for each worker |
| Faster worker | If worker A is k times as fast as B ⇒ R_A = k × R_B |
Useful when converting rates |
3. Common Problem Types
| Problem | Key Idea | How to Approach |
|---|---|---|
| A & B together finish a job | Combined rate = R_A + R_B |
T = W / (R_A+R_B) |
| A works alone for some time, then B joins | Separate phases → add work done in each | Work_A = R_A × t1Work_B = R_B × t2Work_total = Work_A + Work_B |
| One worker leaves | Subtract his contribution from total work | Work_remaining = W – R_left × t_left |
| Two workers work at different rates | Use ratio of speeds | R_A : R_B = 1 : 2 → R_A = 1/3, R_B = 2/3 (if total = 1/day) |
| Work done by one worker alone vs together | Compare time taken | T_A = W / R_A vs T_total = W / (R_A+R_B) |
| Work done in parts | Break job into segments (e.g., 1st part by A, 2nd by B) | Compute each part’s time separately |
4. Worked Example
Problem
A and B can complete a piece of work in 12 days and 15 days respectively. If they work together for 4 days and then B leaves, how many more days will A need to finish the remaining work?
Step‑by‑Step Solution
| Step | Explanation | Calculation |
|---|---|---|
| 1. Find individual rates | Rate = 1 / days per job | R_A = 1/12R_B = 1/15 |
| 2. Combined rate for first 4 days | R_total = R_A + R_B |
R_total = 1/12 + 1/15 = 5/60 + 4/60 = 9/60 = 3/20 |
| 3. Work done in first 4 days | Work_done = R_total × 4 |
Work_done = (3/20) × 4 = 12/20 = 3/5 |
| 4. Remaining work | Work_remaining = 1 – Work_done |
Work_remaining = 1 – 3/5 = 2/5 |
| 5. Time for A alone | T = Work_remaining / R_A |
T = (2/5) / (1/12) = (2/5) × 12 = 24/5 = 4.8 days |
Answer: A needs 4.8 days (≈ 4 days 19 hours) to finish the remaining work.
Tip: Always convert rates to a common denominator first, then simplify.
5. Quick Revision Summary
- Work = Rate × Time – the universal rule.
- Rate of a worker is the part of the job he can finish in one day (or hour).
- Combined rate = sum of individual rates when workers work together.
- Time required =
Work / Combined rate. - Common trick: Convert all rates to a common denominator (e.g., days⁻¹) before adding/subtracting.
- When a worker leaves or joins, treat his contribution as a separate time segment.
- Check units: If work is in “man‑days”, rate is in “work per day”; if time is in hours, convert rates accordingly.
- Always verify the answer by plugging back into the equation:
Rate × Timeshould equal the work (or the remaining work).
6. Quick Practice Questions (Try before the exam)
- **A can finish a job in 20