Puducherry Patwari / Lekhpal /Quantitative Aptitude

Time & work

Commercial Maths · free study notes · Updated

Time & Work – Quantitative Aptitude

Puducherry Patwari / Lekhpal – Study Notes


1. Simple Explanation

Time & Work problems ask you to find how long it takes to complete a task (or how many people are needed) when several workers are involved.

  • Work is a unit of job (e.g., “one whole plot”).
  • Rate (or work‑rate) is the amount of work done per unit time.
    • If a worker completes 1 job in T hours → rate = 1/T jobs/hour.
  • When workers work together, their rates add up.

Key Idea:
[ \text{Total Work} = (\text{Rate of Worker A} + \text{Rate of Worker B} + \dots) \times \text{Time} ]


2. Key Points & Formulas

Concept Formula Explanation
Rate of a worker (r = \dfrac{1}{T}) (T) – time taken by worker to finish 1 job alone.
Combined rate (R = r_1 + r_2 + \dots + r_n) Sum of individual rates.
Time to finish a job together (t = \dfrac{1}{R}) or (t = \dfrac{W}{R}) (W) – total work (usually 1).
Work done by a worker in a given time (W = r \times t)
Work done by a worker in a given time when rate is 1/T (W = \dfrac{t}{T})
Work left after a part has been done (W_{\text{left}} = W_{\text{total}} - W_{\text{done}})
Work after changing team Re‑calculate combined rate and use (t = W_{\text{left}}/R_{\text{new}}).

Common Pitfalls

  1. Confusing “time” with “rate” – always convert time to rate first.
  2. Adding times instead of rates – rates add, times do not.
  3. Assuming the same efficiency – always check if workers have different rates.
  4. Ignoring “work left” – when a worker leaves, compute the remaining work before re‑calculating time.

3. Worked Example

Problem

A and B can complete a piece of land in 12 and 15 days respectively.
A works alone for 3 days, then leaves.
B then works alone for 4 days, after which A returns and works with B.
How many more days will they need to finish the remaining work?

Step‑by‑Step Solution

  1. Find individual rates

    • A’s rate: (r_A = \dfrac{1}{12}) job/day
    • B’s rate: (r_B = \dfrac{1}{15}) job/day
  2. Work done by A in first 3 days
    [ W_{A1} = r_A \times 3 = \frac{1}{12}\times 3 = \frac{1}{4} ]

  3. Work left after A’s first stint
    [ W_{\text{left1}} = 1 - \frac{1}{4} = \frac{3}{4} ]

  4. Work done by B in next 4 days
    [ W_{B1} = r_B \times 4 = \frac{1}{15}\times 4 = \frac{4}{15} ]

  5. Work left after B’s first stint
    [ W_{\text{left2}} = \frac{3}{4} - \frac{4}{15} ] Convert to common denominator (60):
    [ \frac{3}{4} = \frac{45}{60},\quad \frac{4}{15} = \frac{16}{60} ] [ W_{\text{left2}} = \frac{45-16}{60} = \frac{29}{60} ]

  6. Combined rate when A and B work together
    [ R_{AB} = r_A + r_B = \frac{1}{12} + \frac{1}{15} = \frac{5}{60} + \frac{4}{60} = \frac{9}{60} = \frac{3}{20} ]

  7. Time needed to finish remaining work
    [ t_{\text{remaining}} = \frac{W_{\text{left2}}}{R_{AB}} = \frac{\frac{29}{60}}{\frac{3}{20}} = \frac{29}{60} \times \frac{20}{3} = \frac{29 \times 20}{60 \times 3} = \frac{580}{180} = \frac{29}{9} \text{ days} ] [ \frac{29}{9} \approx 3.222\text{ days} ]

Answer: They need approximately 3.22 days (i.e., 3 days and 5 hours) more to finish the land.


4. Quick Revision Summary

  • Rate = 1 / Time (job per hour/day).
  • Rates add when workers work together.
  • Time to finish a job together: (t = \dfrac{1}{\text{combined rate}}).
  • Work done in a given time: (W = r \times t).
  • When team changes, recompute the remaining work and the new combined rate.
  • Always work with common units (hours or days).
  • Check for common denominators when adding/subtracting fractions