CA Final /Economics & Finance

Capital budgeting

Financial Management · free study notes

Capital Budgeting – Quick & Easy Study Notes


1. What is Capital Budgeting?

  • Capital budgeting is the process of deciding which big‑ticket projects a company should invest in.
  • Think of it like choosing a vacation: you look at the cost, the fun factor, and how long you’ll enjoy it before deciding.

2. Why is it Important?

  • It tells the company where to put its money so it grows.
  • Helps avoid wasting money on projects that don’t bring enough return.
  • Keeps the company financially healthy.

3. Key Steps (in plain language)

Step Everyday Analogy What the company does
1. Identify Ideas Scanning a grocery list for items you need List all possible projects (new factory, software, marketing campaign)
2. Estimate Cash Flows Predicting how much money you’ll spend and earn each month Forecast the money that will come in and out of the project each year
3. Pick a Discount Rate Calculating how much a future dollar is worth today Use the company’s cost of capital (interest rate) to value future money
4. Calculate Net Present Value (NPV) Checking if a future gift is worth more than its present value Add up all discounted cash flows and subtract the initial cost
5. Make a Decision Buying the item that gives you the most bang for the buck Choose projects with positive NPV; reject others

4. The Big Numbers

4.1 Net Present Value (NPV)

  • Formula (simple form):
    [ NPV = \sum_{t=0}^{n} \frac{C_t}{(1+r)^t} ] (C_t) = cash flow at time t
    (r) = discount rate (interest rate)
  • Interpretation
    • Positive NPV → Project adds value.
    • Zero NPV → Project breaks even.
    • Negative NPV → Project destroys value.

4.2 Internal Rate of Return (IRR)

  • The rate r that makes NPV = 0.
  • Like finding the interest rate that makes a savings account exactly equal to the cost of a new laptop.

4.3 Payback Period

  • How many years until you recover the initial investment.
  • Quick check but ignores money after that point.

5. Simple Example

Year Cash Flow ($)
0 (now) -$10,000 (investment)
1 +$3,000
2 +$4,000
3 +$4,000
4 +$3,000

Assume discount rate 10%.

  1. Discount each cash flow

    • Year 1: 3,000 / 1.10 = 2,727
    • Year 2: 4,000 / 1.21 = 3,305
    • Year 3: 4,000 / 1.331 = 3,004
    • Year 4: 3,000 / 1.464 = 2,048
  2. Add them up

    • Total discounted inflows = 2,727 + 3,305 + 3,004 + 2,048 = 11,084
  3. Subtract initial cost

    • NPV = 11,084 – 10,000 = $1,084

Result: Positive NPV. The project should be accepted.


6. Quick Checklist

  • List all project ideas.
  • Estimate cash inflows/outflows for each year.
  • Choose a realistic discount rate.
  • Compute NPV (and IRR if needed).
  • Accept projects with NPV > 0.
  • Re‑evaluate if rates or cash flows change.

7. One‑Sentence Summary

Capital budgeting is like picking the best vacation: you compare costs, future enjoyment, and decide which trip (project) gives you the most value for your money.