Time & Work – SSC CPO Quantitative Aptitude
Topic – Time & Work
Exam – SSC CPO (Staff Selection Commission, Combined Probationary Officer)
Focus – Core formulas, common pitfalls, and quick calculation tricks.
1. Simple Explanation
Time & Work problems deal with how long (time) it takes for one or more workers (or machines, etc.) to complete a job (work).
- Work (W) – Total amount of job (usually expressed as 1 job or 100%).
- Worker’s Rate (R) – Portion of work that a worker can finish in one unit of time.
- ( R = \frac{1}{T} ) where T is the time taken by that worker alone to finish the job.
- Combined Rate – If workers work together, rates add up.
- ( R_{\text{combined}} = R_1 + R_2 + \dots + R_n )
- Time Required –
- ( T = \frac{W}{R_{\text{combined}}} )
The key is to convert time to rate (or vice‑versa) and then add or subtract rates.
2. Key Points & Formulae
| Concept | Formula | Notes |
|---|---|---|
| Rate of one worker | ( R = \frac{1}{T} ) | (T) = time (hrs, days, etc.) to finish 1 job alone |
| Combined rate | ( R_{\text{total}} = R_1 + R_2 + … + R_n ) | Add rates when all work simultaneously |
| Time for combined work | ( T_{\text{total}} = \frac{1}{R_{\text{total}}} ) | Since total work = 1 |
| Work done in a given time | ( \text{Work} = R \times t ) | Useful for “work done in x hours” questions |
| Work remaining | ( \text{Remaining} = 1 - \text{Work done} ) | Often used when a worker stops early |
| Work left after one worker leaves | ( T_{\text{remaining}} = \frac{1 - R_1 t_1}{R_2 + R_3 + …} ) | (t_1) = time worked by the departed worker |
| Work per unit time of two workers | ( R_2 = \frac{R_1}{k} ) (if one is k times slower/faster) | Helpful when rates are given in ratio |
| Common trick | Convert all times to a common unit (hrs or days) before calculations. | Reduces errors in mixed‑unit problems. |
| Common pitfall | Forgetting to add the remaining work when a worker leaves. | Always compute the amount left before the new rate. |
| Common trick | “Work” ≈ “Job” – treat the whole job as 1 unit. | Keeps algebra simple, especially for ratios. |
3. Worked Example (Typical SSC CPO)
Problem
A and B can do a piece of work in 30 days and 45 days respectively. They work together for 10 days. Then B leaves and C who can finish the same work in 20 days joins. How many more days will the remaining work take?
Step‑by‑Step
-
Find rates
- ( R_A = \frac{1}{30} ) job/day
- ( R_B = \frac{1}{45} ) job/day
- ( R_C = \frac{1}{20} ) job/day
-
Combined rate of A & B for first 10 days
- ( R_{AB} = R_A + R_B = \frac{1}{30} + \frac{1}{45} = \frac{3+2}{90} = \frac{5}{90} = \frac{1}{18} ) job/day
- Work done in 10 days: ( W_{AB} = R_{AB} \times 10 = \frac{1}{18} \times 10 = \frac{10}{18} = \frac{5}{9} )
-
Work remaining after 10 days
- ( W_{\text{rem}} = 1 - \frac{5}{9} = \frac{4}{9} )
-
Now A and C work together
- Combined rate ( R_{AC} = R_A + R_C = \frac{1}{30} + \frac{1}{20} = \frac{2+3}{60} = \frac{5}{60} = \frac{1}{12} ) job/day
-
Time needed for remaining work
- ( T_{\text{rem}} = \frac{W_{\text{rem}}}{R_{AC}} = \frac{\frac{4}{9}}{\frac{1}{12}} = \frac{4}{9} \times 12 = \frac{48}{9} = \frac{16}{3} = 5\frac{1}{3} ) days
Answer: 5 ⅓ days (or 5 days and 8 hours).
4. Quick Revision Summary
- Rate = 1 / Time – always convert time to rate.
- Add rates when workers act together.
- Time = 1 / Combined Rate – the job = 1 unit.
- Track remaining work if someone stops or joins late.
- Use common units (days or hours) to avoid mix‑ups.
- Check with a quick sanity test:
- If a worker alone does the job in 20 days, working for 10 days alone should finish half the job.
- If the answer is outside this logical range, re‑check calculations.
Quick Cheat‑Sheet
| Situation | Rate (job/day) | Time (days) |
|---|---|---|
| A alone | (1/30) | 30 |
| B alone | (1/45) | 45 |
| C alone | (1/20) | 20 |
| A+B together | (1/18) | 18 |
| A+C together | (1/12) | 12 |
(Use these numbers directly in your calculations.)
Tip for SSC CPO – On the exam, you often have to solve such problems in 2–3 minutes.