Time & Work – SBI PO Study Notes
(Quantitative Aptitude – Time & Work)
Why it matters
In the SBI PO exam, “Time & Work” problems test your ability to translate real‑world situations into mathematical equations and solve them efficiently. Mastery of this topic gives you a strong advantage in the quantitative section.
1. Simple Explanation
| Concept | What it Means | Example |
|---|---|---|
| Rate of work | Work done per unit time (e.g., workers per hour). | 1 worker completes a task in 4 hrs → Rate = 1/4 task/hr |
| Work (W) | Total amount of job to be done (usually expressed as “1 job”). | Building a wall = 1 wall |
| Time (T) | Total time to finish the job (hrs, days, etc.). | 6 hrs |
| Work Equation | (W = \text{Rate} \times \text{Time}) | (1 = \frac{1}{4}\times 4) |
Key Idea – If you know any two of the three quantities (W, Rate, Time), you can find the third.
2. Key Points & Formulas
| Scenario | Formula | Notes |
|---|---|---|
| Single worker | (T = \dfrac{W}{\text{Rate}}) | Rate = 1/T if W = 1 |
| Two workers working together | (\text{Rate}_{\text{total}} = r_1 + r_2) | Total time = (W / (r_1 + r_2)) |
| n workers with different rates | (T = \dfrac{W}{\sum_{i=1}^{n} r_i}) | Use rates in same units |
| Work done in part of the job | ( \text{Work done} = \text{Rate} \times \text{Time} ) | Subtract from total to find remaining work |
| Worker stops after some time | Let (t_d) be duration worker works, (t_s) be after stopping. (W = r,t_d + r_2,t_s) |
Solve for unknown time or rate |
| Relative speeds | If worker A is k times faster than B: (r_A = k,r_B) |
Useful for “A does in 3 hrs, B in 5 hrs” type |
| Combining rates | (\frac{1}{T_{\text{combined}}} = \frac{1}{T_1} + \frac{1}{T_2}) | Works when each worker’s time to finish alone is given |
Common Tricks
- Convert to “per hour” when times are in days or minutes.
- Use “work done” as the numerator and “time” as the denominator to keep fractions simple.
- When a worker does X% of the job in Y hours, the remaining work is ((100-X)%).
- Avoid cancellation errors – always keep units (hrs, days) consistent.
3. Worked Example
Problem
Three workers – A, B and C – can complete a job in 12, 15 and 20 hours respectively.
A works alone for 2 hrs and then leaves. B and C together finish the remaining work in 5 hrs.
How many hours would B alone take to finish the whole job?
Solution
-
Rates
- (r_A = \dfrac{1}{12}) job/hr
- (r_B = \dfrac{1}{15}) job/hr
- (r_C = \dfrac{1}{20}) job/hr
-
Work done by A in 2 hrs
[ W_{A} = r_A \times 2 = \frac{1}{12}\times 2 = \frac{1}{6}\ \text{job} ] -
Remaining work
[ W_{\text{rem}} = 1 - \frac{1}{6} = \frac{5}{6}\ \text{job} ] -
Combined rate of B & C
[ r_{BC} = r_B + r_C = \frac{1}{15} + \frac{1}{20} ] Find common denominator 60:
[ r_{BC} = \frac{4}{60} + \frac{3}{60} = \frac{7}{60}\ \text{job/hr} ] -
Time taken by B & C together
[ T_{BC} = \frac{W_{\text{rem}}}{r_{BC}} = \frac{\frac{5}{6}}{\frac{7}{60}} = \frac{5}{6} \times \frac{60}{7} = \frac{300}{42} = 7.\overline{14}\ \text{hours} ] But problem says they finish in 5 hrs → contradiction.
Wait – we mis‑read the problem.
Actually, the statement: “B and C together finish the remaining work in 5 hrs.”
So the remaining work is (5) hrs × (r_{BC}).
Let's compute work done by B & C in 5 hrs: [ W_{BC} = r_{BC} \times 5 = \frac{7}{60}\times5 = \frac{35}{60} = \frac{7}{12}\ \text{job} ] -
Check consistency
Work done by A (1/6) + Work done by B & C (7/12)
[ \frac{1}{6} + \frac{7}{12} = \frac{2}{12} + \frac{7}{12} = \frac{9}{12} = \frac{3}{4} ] So only 3/4 of the job is finished – something is wrong.