Time & Work – Quantitative Aptitude (SBI PO)

Audience: Students preparing for SBI PO and IIT‑JEE style quantitative aptitude tests.
Goal: Master the concepts, derive the key formulas, identify common pitfalls, and solve hard problems efficiently.


1. Core Idea

  • Work is a quantity that can be added or subtracted linearly.
  • Rate of work (e.g., workers per hour) is the inverse of the time required to complete a unit of work.
  • When multiple agents (workers, machines, people) work together, their rates add.

2. Basic Definitions

Symbol Meaning Unit
(W) Total work (units, e.g., man‑hours, tasks) units
(t) Time taken hours
(R) Rate of work units/hour
(n) Number of workers / machines count
(k) Proportion of work done (0 ≤ k ≤ 1) dimensionless

Fundamental relation

[ R = \frac{W}{t}\quad\text{or}\quad W = R \times t ]


3. Deriving the “Rate + Time + Work” Formula

Starting from the basic definition:

[ R = \frac{W}{t} ]

Multiplying both sides by (t):

[ W = R \times t ]

If two agents work together, their rates add:

[ R_{\text{total}} = R_1 + R_2 + \dots + R_n ]

Hence

[ W = (R_1 + R_2 + \dots + R_n) \times t ]


4. Working with Multiple Workers

4.1 Equal Work Rates

If (n) workers each do the same job independently:

[ R_i = r \quad \forall i ]

Then

[ R_{\text{total}} = n r ]

If they finish a job in (t) hours:

[ W = n r t ]


4.2 Different Work Rates

Let worker (A) finish a job in (t_A) hours and worker (B) in (t_B) hours.

  • Their individual rates: [ R_A = \frac{W}{t_A}, \quad R_B = \frac{W}{t_B} ]

  • Combined rate: [ R_{AB} = \frac{W}{t_A} + \frac{W}{t_B} = W\left(\frac{1}{t_A} + \frac{1}{t_B}\right) ]

  • Time to finish together: [ t_{AB} = \frac{W}{R_{AB}} = \frac{1}{\frac{1}{t_A} + \frac{1}{t_B}} = \frac{t_A t_B}{t_A + t_B} ]

Key Result: When two workers work together, the combined time is the harmonic mean of their individual times.


5. Work Done in a Fraction of Time

If a worker works for only a part of the job:

[ \text{Work done} = R \times t_{\text{part}} ]

  • Example: A worker can finish a job in 20 h. If he works only 5 h, he completes (\frac{5}{20} = \frac{1}{4}) of the work.

6. Work & Wage

Often the problem gives wage (W) per unit time. Since (R = W/t), the wage is proportional to the rate. Thus:

[ \text{Wage} : \text{Rate} = \text{constant} ]

If two workers have wages (w_1, w_2) and times (t_1, t_2) respectively:

[ \frac{w_1}{w_2} = \frac{t_2}{t_1} ]


7. Common Tricky Points

Tricky Point Why it’s tricky How to handle
Mixed units (e.g. workers per day vs. per hour) Confusion in rate conversion Convert all to a common unit (e.g., hour) before adding rates
Partial work (e.g., after 2 workers left) Work done before and after change must be summed Compute work done in each segment separately; use remaining work for next segment
Work done by machines & humans Machines may have fixed rates, humans variable Treat each as an independent rate; add them together
Wage vs. time Higher wage might mean faster work Use proportion (w_1:w_2 = t_2:t_1) or directly compute rates
Non‑linear work (e.g., rate decreases as fatigue sets in) Not covered by linear model For exam problems, assume linear unless otherwise stated

8. Important Formulae (Quick Reference)

Scenario Formula Explanation
One worker alone (t = \frac{W}{R}) Time to finish job
Two workers together (t_{AB} = \frac{t_A t_B}{t_A + t