📚 Time & Work – Quick & Easy Study Notes
(For SBI PO Quantitative Aptitude – Beginner Level)
1️⃣ What is “Time & Work”?
- Work: The whole job that needs to be finished (e.g., painting a wall, filling a bucket).
- Rate: How fast a person or machine can work – think of it as “how many units of the job they finish in one day.”
- Time: How long it takes to finish the job.
Analogy
Imagine you have a big pizza (the job).
Rate = how many slices you can eat per minute.
Time = how many minutes you spend eating.
Work = the whole pizza.
2️⃣ Core Formulae (No Jargon)
| What you need | Formula (in plain words) |
|---|---|
| Work done | Work = Rate × Time |
| Rate | Rate = Work ÷ Time |
| Combined Rate (when people work together) | Rate_total = Rate_A + Rate_B + … |
| Time together | Time = Work ÷ Rate_total |
Remember:
• Work is usually 1 job (whole job).
• Rate is usually expressed as “job per day”.
• Time is in days (or hours, if you convert).
3️⃣ Step‑by‑Step Approach
-
Write what you know
- Example: A can finish the job in 10 days → Rate_A = 1/10 job per day.
-
Find missing rates or times
- Use the formula Rate = 1 / Time (if time is given).
-
Add rates for people working together
- Rate_total = Rate_A + Rate_B …
-
Compute the required time
- Time_needed = 1 ÷ Rate_total
-
Check the answer
- Make sure the number is reasonable (no negative time, etc.).
4️⃣ Tiny Examples
Example 1 – One Worker
- Question: A can finish the job in 8 days.
- Rate_A = 1/8 job per day.
- Time if A works alone = 8 days.
Example 2 – Two Workers Together
- Question: A works in 5 days, B in 10 days. How long together?
- Rate_A = 1/5, Rate_B = 1/10.
- Rate_total = 1/5 + 1/10 = 3/10 job/day.
- Time = 1 ÷ (3/10) = 10/3 ≈ 3.33 days.
Example 3 – Three Workers
- A: 6 days, B: 9 days, C: 12 days.
- Rates: 1/6, 1/9, 1/12 → add → 1/6 + 1/9 + 1/12 = 15/36 = 5/12.
- Time = 1 ÷ (5/12) = 12